Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-06-18⁩
ApprovedDMD-2026-004Aleppo 230 kV Substations Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Aleppo 230 kV Substations Rehabilitation
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1The proposalAuto-filled

TitleAuto-filled
Aleppo 230 kV Substations Rehabilitation
Proposed byAuto-filled
Eng. Maher Al-Hamawi
DepartmentAuto-filled
Energy, Water & Utilities Projects Directorate
Submitted onAuto-filled
⁦2023-06-18⁩
Proposal numberAuto-filled
DMD-2026-004

2Justification

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

3Objectives

  1. Rehabilitate core energy, water and transport infrastructure
  2. Stimulate growth, restore production and attract investment

Strategic objectives served

  • SO-2.1 — Rehabilitate core energy, water and transport infrastructure
  • SO-1.1 — Stimulate growth, restore production and attract investment

4Expected benefits

KindBenefit
ProductivityDaily supply hours in the Aleppo neighbourhoods served — target 43800 hours / year

5Cost & feasibility

Estimated cost

SYP 10.3B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 7.4B
Supervision & consultingSYP 1.4B
Internal teamSYP 927.5M
Contingency reserve (5%)SYP 515M
TotalSYP 10.3B

6Initial risks

RiskLevelProposed response
Main contractor cash-flow trouble and late payment of subcontractorsHighTreated in the risk management plan
Control-room fire systems not meeting civil-defence requirementsHighTreated in the risk management plan
Faults in the new transformers during commissioningMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2023-06-18⁩ 12:45
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2023-06-20⁩ 10:55
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2023-06-25⁩ 11:02
4Portfolio manager reviewTechnical acceptanceEng. Rami YoussefPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-06-26⁩ 12:09
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2023-06-29⁩ 08:00
6Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2023-07-02⁩ 12:21
7Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2023-07-06⁩ 08:00
8Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2023-07-09⁩ 14:23

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2023-06-20⁩

PMO review

Mariam Al-Zoubi

Approved⁦2023-06-25⁩

Portfolio manager review

Eng. Rami Youssef

Approved⁦2023-06-26⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2023-07-02⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2023-07-09⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2023-06-18⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2023-06-20⁩ at ⁦10:55⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2023-06-25⁩ at ⁦11:02⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2023-06-26⁩ at ⁦12:09⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2023-07-02⁩ at ⁦12:21⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2023-07-09⁩ at ⁦14:23⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-07-09⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Maher Al-Hamawi

  2. V1Returned for edit⁦2023-06-18⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Maher Al-Hamawi