PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

Aleppo 230 kV Substations Rehabilitation

PRJ-2026-004 · Development Projects Follow-up Sector · Operational · WP-2024-004

StalledCritical4ExecutionProject manager: Eng. Maher Al-Hamawi · Sponsor: Salma Al-Zaim
Progress
⁦68%⁩ / ⁦92%⁩
SPI · CPI
0.74 · 0.84
Spend
SYP 8.3B / SYP 10.3B
Estimate at completion
SYP 12.3B

Schedule

⁦24%⁩ behind⁦68%⁩

Planned to date ⁦92%⁩

Forecast finish: 2027-02-03 · 126 days late

SPI0.74Schedule performance index · 0.74CPI0.84Cost performance index · 0.84

Health dimensions

Critical

Last update: 2026-10-21 · Up to date

Deliverables

⁦5⁩ of ⁦12⁩ due deliverables accepted on time (⁦42%⁩)

Next milestones

  • Testing & acceptance complete2027-02-16
  • Final handover2027-03-08

Top risks

  • Main contractor cash-flow trouble and late payment of subcontractors25
  • Control-room fire systems not meeting civil-defence requirements15
  • Faults in the new transformers during commissioning12

Open impediments

  • Site workers stopped 4 days over late wages · Escalated
  • Oil leak in the station 2 transformer during testing · Open
  • Incomplete bills of quantities attached to certificate 33 · Open

Decisions and changes waiting

  • Direct payment to subcontractors on the Aleppo substations

Copilot summary

The scope holds 1 project with a budget of SYP 10.3bn: 0 on track and 1 red or critical. Weighted progress is 68% against 92% planned, spend SYP 8.34bn, and EAC SYP 12.26bn (SYP 1.96bn over).

1 project is more than a month behind baseline; the worst: Aleppo 230 kV Substations Rehabilitation (126 days).