Project status card
28 October 2026
Aleppo 230 kV Substations Rehabilitation
PRJ-2026-004 · Development Projects Follow-up Sector · Operational · WP-2024-004
- Progress
- 68% / 92%
- SPI · CPI
- 0.74 · 0.84
- Spend
- SYP 8.3B / SYP 10.3B
- Estimate at completion
- SYP 12.3B
Schedule
Planned to date 92%
Forecast finish: 2027-02-03 · 126 days late
SPI0.74Schedule performance index · 0.74CPI0.84Cost performance index · 0.84Health dimensions
Last update: 2026-10-21 · Up to date
Deliverables
5 of 12 due deliverables accepted on time (42%)
Next milestones
- Testing & acceptance complete2027-02-16
- Final handover2027-03-08
Top risks
- Main contractor cash-flow trouble and late payment of subcontractors25
- Control-room fire systems not meeting civil-defence requirements15
- Faults in the new transformers during commissioning12
Open impediments
- Site workers stopped 4 days over late wages · Escalated
- Oil leak in the station 2 transformer during testing · Open
- Incomplete bills of quantities attached to certificate 33 · Open
Decisions and changes waiting
- Direct payment to subcontractors on the Aleppo substations
Copilot summary
The scope holds 1 project with a budget of SYP 10.3bn: 0 on track and 1 red or critical. Weighted progress is 68% against 92% planned, spend SYP 8.34bn, and EAC SYP 12.26bn (SYP 1.96bn over).
1 project is more than a month behind baseline; the worst: Aleppo 230 kV Substations Rehabilitation (126 days).