Integrated Public Financial Management System — Phase 1
Remove from watchlistOne system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.
Budget (BAC)
Actual cost
69% of budget
Progress
Estimate at completion
+SYP 219.9M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-22 | 2025-09-26 | +96 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-24 | 2026-04-12 | +170 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-04-27 | 2026-11-27 | +214 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-29 | 2027-01-12 | +136 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-02-27 | +58 days | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
61%Awaiting acceptance
11%Not handed in
28%Deliverable flow
Display options
| Project plan & baseline001-D1 | 5% | CRT-001-01 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Rasha Al-Mudarres | 2025-04-21 | V1 | 3 of 3 |
| Monitoring & reporting001-D2 | 4% | CRT-001-02 | Approved | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2025-06-22 | V1 | 3 of 3 |
| Business requirements001-D3 | 10% | CRT-001-03 | Approved | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2025-08-23 | V1 | 3 of 3 |
| Solution design001-D4 | 10% | CRT-001-04 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Rasha Al-Mudarres | 2025-10-24 | V1 | 3 of 3 |
| Release 1001-D5 | 16% | CRT-001-05 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Rasha Al-Mudarres | 2025-12-25 | V1 | 3 of 3 |
| Release 2001-D6 | 16% | CRT-001-06 | Approved | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Rasha Al-Mudarres | 2026-02-25 | V1 | 3 of 3 |
| Integrations001-D7 | 11% | — | Under review | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2026-04-27 | V1 | 1 of 3 |
| System testing001-D8 | 8% | — | Draft | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Rasha Al-Mudarres | 2026-06-28 | V0 | 0 of 3 |
| User acceptance testing001-D9 | 8% | — | Draft | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2026-08-29 | V0 | 0 of 3 |
| Training & change001-D10 | 6% | — | Draft | Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy | Rasha Al-Mudarres | 2026-10-30 | V0 | 0 of 3 |
| Go-live & handover001-D11 | 6% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Rasha Al-Mudarres | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |