PRJ-2026-001Off track4ExecutionHybridStalledDelivered by:Ministry of Finance

Integrated Public Financial Management System — Phase 1

Remove from watchlist

One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 1.6B

Actual cost

SYP 1.1B

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 1.8B

+SYP 219.9M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-06-16⁩
ApprovedDMD-2026-001Integrated Public Financial Management System — Phase 1

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-001
Project
Integrated Public Financial Management System — Phase 1
Portfolio
Government Digital Infrastructure & Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Salma Al-Zaim
Project manager
Nour Al-Jabiri

1The proposalAuto-filled

TitleAuto-filled
Integrated Public Financial Management System — Phase 1
Proposed byAuto-filled
Nour Al-Jabiri
DepartmentAuto-filled
Government Systems & Integration Directorate
Submitted onAuto-filled
⁦2024-06-16⁩
Proposal numberAuto-filled
DMD-2026-001

2Justification

One system for budget preparation and execution, government accounting and payroll across the ministries — it ties investment spending to the plan’s projects and gives the Ministry of Finance and the Authority a daily view of spend.

3Objectives

  1. Sound governance and effective follow-up of projects and data
  2. Stimulate growth, restore production and attract investment

Strategic objectives served

  • SO-5.2 — Sound governance and effective follow-up of projects and data
  • SO-1.1 — Stimulate growth, restore production and attract investment

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 1.6B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 1.2B
Supervision & consultingSYP 227.5M
Internal teamSYP 145M
Contingency reserve (5%)SYP 80M
TotalSYP 1.6B

6Initial risks

RiskLevelProposed response
Customisation and ministry-systems integration cost above the approved reserveHighTreated in the risk management plan
Late migration and reconciliation of historical financial dataMediumTreated in the risk management plan
Implementation consultants’ contracts ending before go-liveMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nour Al-JabiriDirector, Government Systems & IntegrationSubmitted—⁦2024-06-16⁩ 09:24
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2024-06-17⁩ 13:04
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-06-20⁩ 14:11
4Portfolio manager reviewTechnical acceptanceEng. Mazen KassabPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-06-23⁩ 09:18
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-06-24⁩ 09:00
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2024-06-26⁩ 11:32

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2024-06-17⁩

PMO review

Mariam Al-Zoubi

Approved⁦2024-06-20⁩

Portfolio manager review

Eng. Mazen Kassab

Approved⁦2024-06-23⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2024-06-24⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2024-06-26⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Nour Al-Jabiri on ⁦2024-06-16⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2024-06-17⁩ at ⁦13:04⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-06-20⁩ at ⁦14:11⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Mazen Kassab · Portfolio manager

    Approved · ⁦2024-06-23⁩ at ⁦09:18⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-06-24⁩ at ⁦09:00⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2024-06-26⁩ at ⁦11:32⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-07-07⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Nour Al-Jabiri

  2. V1Returned for edit⁦2024-06-16⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal