SO-2.1 · Rehabilitate core energy, water and transport infrastructure

Renewable energy & non-conventional water

On holdDelivered wholly through projectsReconstruction & Infrastructure

The 20 MW Qalamoun solar field and the Baniyas pilot seawater desalination plant.

⁦42%⁩

Initiative weighted progress

⁦42.4%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦42.4%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

SYP3.2B

2 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
20 MW Qalamoun Solar Field

PRJ-2026-010

Primary⁦70%⁩⁦58%⁩⁦40.6%⁩
Baniyas Pilot Seawater Desalination Plant

PRJ-2026-026Suspended — progress frozen at its last approved value

Primary⁦30%⁩⁦6%⁩⁦1.8%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦42.4%⁩ points ÷ shares counted ⁦100%⁩ = ⁦42.4%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦42.4%⁩

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

The 20 MW Qalamoun solar field and its grid link, and the Baniyas pilot seawater desalination plant.

Outputs

  • A 20 MW solar field
  • A pilot desalination plant

Delivery phases

  • Solar field

    2025-03-02 — 2027-04-22

  • Desalination plant

    2026-02-01 — 2027-10-31

Today · 2026-10-28

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: 20 MW Qalamoun Solar Field

1Deliverable weight in the project

⁦38.0%⁩

Weight of «Civil works» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦20.9%⁩

Its relative weight in Energy & Water Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦70%⁩

Its contribution to «Renewable energy & non-conventional water»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Obstacle in the wayMediumOpen

    The desalination plant is on hold pending an investment-plan allocation

    Response: Put it to the project approval committee with an updated feasibility study

    Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy

Deviation

Budget: projects total SYP 3.2B against the estimate SYP 3.3B

Schedule: last project ends ⁦2027-10-31⁩ against the initiative end ⁦2027-10-31⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Higher Council resolution HCED-2026-032026-03-25

No change requests on this item since the plan was approved.