SO-6.2 · Governorate plans and a balanced share of public investment

National indicators & plan follow-up

At riskDelivered wholly through projectsBalanced Local Development across the Governorates

Official statistical indicators published for every governorate and sector, and a tracker that follows the medium-term plan in the ministries and governorates from approval to delivery.

⁦40%⁩

Initiative weighted progress

⁦40.3%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦40.3%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

SYP1.2B

2 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
National Statistical Indicators & Open Data Portal

PRJ-2026-016

Primary⁦55%⁩⁦62%⁩⁦34.1%⁩
Medium-Term Plan Implementation Tracker (ministries & governorates)

PRJ-2026-023

Primary⁦35%⁩⁦1%⁩⁦0.4%⁩
Unified Government e-Services Platform

PRJ-2026-014

Secondary⁦10%⁩⁦58%⁩⁦5.8%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦40.3%⁩ points ÷ shares counted ⁦100%⁩ = ⁦40.3%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦40.3%⁩

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

The national statistical indicators & open-data portal and its data governance, and the medium-term plan implementation tracker in the ministries and governorates.

Outputs

  • The national indicators portal with monthly indicators per governorate
  • The medium-term plan implementation tracker
  • An open statistical data publication policy

Delivery phases

  • National portal & data governance

    2025-08-03 — 2027-01-18

  • Plan tracker

    2026-09-06 — 2027-12-31

  • Link to ministry and governorate reports

    2027-04-01 — 2027-12-31

Today · 2026-10-28

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: National Statistical Indicators & Open Data Portal

1Deliverable weight in the project

⁦40.0%⁩

Weight of «Build» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦17.3%⁩

Its relative weight in Digital Government Services & Data Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦55%⁩

Its contribution to «National indicators & plan follow-up»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Obstacle in the wayHighBeing treated

    Two data-engineer posts vacant since June

    Response: A temporary services contract until the posts are filled

    Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy
  • Possible riskMediumOpen

    Ministries and governorates slow to send delivery reports

    Response: A quarterly reporting schedule followed up through the governorate planning directorates

    Iman Al-JasemIman Al-JasemDirector General, Medium-Term PlanP-048iman.aljasem@psa.gov.sy

Deviation

Budget: projects total SYP 1.2B against the estimate SYP 1.3B

Schedule: last project ends ⁦2027-12-31⁩ against the initiative end ⁦2027-12-31⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Higher Council resolution HCED-2026-032026-03-25

No change requests on this item since the plan was approved.