PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Electronic forms

The project’s twelve forms with their status and approval path, each printable with its approval log.

Forms

14

In approval

0

Past their limit

0

Escalated automatically

0

Approved

13

1PSA-PMO-F01Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

ApprovedV2 · ⁦2025-03-16⁩

2PSA-PMO-F02Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

ApprovedV4 · ⁦2025-05-10⁩

3PSA-PMO-F03Approval

Project weight

The weight and the relative weight in the portfolio

ApprovedV2 · ⁦2026-09-16⁩

4PSA-PMO-F04Initiation

Project charter

Objective, scope, deliverables, roles and budget

ApprovedV2 · ⁦2025-10-10⁩

5PSA-PMO-F05Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

ApprovedV2 · ⁦2025-11-06⁩

6PSA-PMO-F06Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

ApprovedV1 · ⁦2025-10-19⁩

9PSA-PMO-F09Execution

Change request

The change, its impact analysis and the approval decision

Not yet · Opens at the «Execution» stage

10PSA-PMO-F10Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Not yet · Opens at the «Execution» stage

11PSA-PMO-F11Execution

Corrective plan

Actions, owners, dates and status

Not yet · Opens at the «Execution» stage

12PSA-PMO-F12Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Not yet · Opens at the «Closure» stage