PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started