Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 1.1B split into spent, committed and left, with the estimate at completion

EAC SYP 1B
Revised request SYP 1.1B
  • Actual spendSYP 370.6M
  • Committed, not spentSYP 529.4M
  • Allotted, uncommittedSYP 118.5M
  • Contingency availableSYP 31.5M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 977.5M
Original budgetwhen the first baseline was approved
SYP 1.1B
Approved budgetafter approved change requests
SYP 1.1B
Current budgetavailable to spend now
SYP 1.1B
Revised budgetif the pending changes are approved
SYP 1.1B

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 900M
Contracts1 active contract
SYP 825M
Purchase orders⁦2⁩ orders
SYP 75M
Remaining budgetapproved less actual
SYP 679.4M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 370.6M
Accrualswork done, not yet invoiced
SYP 14.8M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 1B
ContingencySYP 21M drawn of SYP 52.5M
SYP 31.5M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 977.5M
ApprovedSYP 1.1B
Estimate at completionSYP 1B
Approved is SYP 72.5M (⁦7.4%⁩) above the estimate
The estimate at completion is SYP 51.9M (⁦5.3%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-07-29⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-41025
  • WBS elements⁦5⁩ elements · P-2026-025.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦7⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 21M drawn of SYP 52.5M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 21M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance61.1161.7961.7961.79⁦−0.68⁩
2Design & permits122.22123.58123.58123.58⁦−1.36⁩
3Civil works387.03349.61185.23384.90⁦+2.13⁩
4MEP works305.55248.890.00302.32⁦+3.23⁩
5Handover142.59116.150.00141.08⁦+1.51⁩
Unallocated contingency31.500.000.0015.75⁦+15.75⁩
Total1,050.00900.00370.591,029.41⁦+20.59⁩

Budget split

WBS

SYP 1.1B

Budget

  • Management & governanceSYP 61.1M⁦6%⁩
  • Design & permitsSYP 122.2M⁦12%⁩
  • Civil worksSYP 387M⁦37%⁩
  • MEP worksSYP 305.6M⁦29%⁩
  • HandoverSYP 142.6M⁦14%⁩
  • Unallocated contingencySYP 31.5M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-05-28⁩+241

SPI(t) ⁦0.75⁩ against the approved finish ⁦2027-09-30⁩

Planned valuePV
SYP 590.5M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 378M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 370.6M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 1.1B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+7.41⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−212.47⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.02
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.64
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 1B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 658.8M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+20.59⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.99
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 1B
  • If the rest goes to planSYP 1B
  • At cost and schedule performanceSYP 1.4B
  • The PM’s bottom-up estimateSYP 1B
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 1B

Variance at completion: ⁦+20.59⁩ SYP M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close