PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Suwayda Drinking-Water Network from Al-Ain Dam

APPROVEDV2Approved ⁦2025-10-10⁩

1Project identity

Required at this stage
Project name
Suwayda Drinking-Water Network from Al-Ain Dam
Project code
PRJ-2026-025
Project sponsor
Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy
Project manager
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy
Project owner
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
Portfolio & programme
Energy & Water PortfolioEnergy & Water Systems Rehabilitation Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

3Objectives

Required at this stage
  1. 1Rehabilitate core energy, water and transport infrastructure
  2. 2Comparable public-service quality in every governorate

4Scope

Required at this stage

In scope

  • Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2An approved plan to keep services running for residents during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2025-11-10⁩
2Main deliverable — stage 1⁦2026-10-13⁩
3Main deliverable — final stage⁦2027-06-21⁩
4Final report⁦2027-09-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-10-10⁩
  2. Contract signed⁦2026-02-04⁩
  3. 50% of works complete⁦2026-10-13⁩
  4. Provisional acceptance⁦2027-08-04⁩
  5. Closure⁦2027-09-30⁩

8Budget

Required at this stage
  • Main contract⁦71.9%⁩SYP755M
  • Supervision & consulting⁦14.0%⁩SYP147.5M
  • Internal team⁦9.0%⁩SYP95M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP52.5M
The delivering body’s investment-plan allocationsTotalSYP1.1B

9Timeline

Required at this stage
Start
2025-10-1212 October 2025
Baseline finish
2027-09-3030 September 2027
Duration
⁦24⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority