PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-10-10⁩
ApprovedPRJ-2026-025Suwayda Drinking-Water Network from Al-Ain Dam

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-025
Project
Suwayda Drinking-Water Network from Al-Ain Dam
Portfolio
Energy & Water Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Rami Youssef

1Objective

Background

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Project objectives

  1. Rehabilitate core energy, water and transport infrastructure
  2. Comparable public-service quality in every governorate

2Scope

In scope

  • Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-11-10⁩
Main deliverable — stage 1⁦2026-10-13⁩
Main deliverable — final stage⁦2027-06-21⁩
Final report⁦2027-09-30⁩
MilestoneDate
Charter approved⁦2025-10-10⁩
Contract signed⁦2026-02-04⁩
50% of works complete⁦2026-10-13⁩
Provisional acceptance⁦2027-08-04⁩
Closure⁦2027-09-30⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Bashir Al-Tai
Project ownerAuto-filled
Eng. Wassim Al-Azm
Project managerAuto-filled
Eng. Rami Youssef
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 755M
Supervision & consultingSYP 147.5M
Internal teamSYP 95M
Contingency reserve (5%)SYP 52.5M
Approved budgetSYP 1.1B

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Rami YoussefDirector, Renewable Energy & Environment ProjectsSubmitted—⁦2025-10-01⁩ 10:00
2PMO complianceMethodology reviewDr. Reem Al-QabbaniPMO — directorApproved—⁦2025-10-04⁩ 12:30
3Project ownerTechnical acceptanceEng. Wassim Al-AzmProject ownerApproved—⁦2025-10-07⁩ 09:45
4Budget funding confirmedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-10-08⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Bashir Al-TaiProject sponsorApproved—⁦2025-10-10⁩ 11:00

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Approved⁦2025-10-04⁩

Project owner

Eng. Wassim Al-Azm

Approved⁦2025-10-07⁩

Budget funding confirmed

Rasha Al-Mudarres

Approved⁦2025-10-08⁩

Sponsor approval

Eng. Bashir Al-Tai

Approved⁦2025-10-10⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. Rami Youssef on ⁦2025-10-01⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director

    Approved · ⁦2025-10-04⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2025-10-07⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-08⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Bashir Al-Tai · Project sponsor

    Approved · ⁦2025-10-10⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-10⁩

    Approved version

    • PMO comments addressed

    Eng. Rami Youssef

  2. V1Returned for edit⁦2025-09-21⁩

    First draft

    • Returned to detail the budget

    Eng. Rami Youssef

Esc