PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy
Suwayda Drinking-Water Network from Al-Ain Dam
Add to watchlistRehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.
Project managerEng. Rami YoussefProject sponsorEng. Bashir Al-TaiProgrammeEnergy & Water Systems Rehabilitation Programme
Budget (BAC)
SYP 1.1B
Actual cost
SYP 370.6M
35% of budget
Progress
36%Awaiting acceptance 12%
Estimate at completion
SYP 1B
SPI · CPI
1.03Schedule performance index · 1.031.02Cost performance index · 1.02
Forecast finish
2027-09-30
On baseline
ExecutionStage 4 of 5
Next gate:Closure4 August 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started