Original
Original baseline
- Finish
- 2027-09-30
- Budget
- SYP 1.1B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-10-12 · by Eng. Bashir Al-Tai
Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.
Budget (BAC)
Actual cost
35% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure4 August 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-10-12 · by Eng. Bashir Al-Tai
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Rami Youssef
What changed from version A to version B
Finish
2027-09-302027-10-04
+4 days
Budget
SYP 1.1BSYP 1.1B
0.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference