PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
1On track
2At risk
0Late
Average delay31 days
Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27Oct 27
Contractual
Build completePlanned: ⁦2026-12-19⁩Forecast / actual: ⁦2027-02-06⁩Delay: 49 daysG3 +49
Executive
Project plan approvedPlanned: ⁦2026-03-09⁩Forecast / actual: ⁦2026-04-07⁩Delay: 29 daysG1 +29
Payment
Final handoverPlanned: ⁦2027-09-30⁩Forecast / actual: ⁦2027-10-04⁩Delay: 4 daysG5 +4
Regulatory
Testing & acceptance completePlanned: ⁦2027-06-08⁩Forecast / actual: ⁦2027-06-30⁩Delay: 22 daysG4 +22
Project
Designs approvedPlanned: ⁦2026-07-01⁩Forecast / actual: ⁦2026-08-21⁩Delay: 51 daysG2 +51

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-03-09⁩⁦2026-04-07⁩⁦+29⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2026-07-01⁩⁦2026-08-21⁩⁦+51⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-12-19⁩⁦2027-02-06⁩⁦+49⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-06-08⁩⁦2027-06-30⁩⁦+22⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2027-09-30⁩⁦2027-10-04⁩⁦+4⁩ daysEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦36%⁩

Awaiting acceptance

⁦12%⁩

Not handed in

⁦52%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline025-D1⁦4%⁩CRT-025-01ApprovedEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syEng. Wassim Al-Azm⁦2026-01-11⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting025-D2⁦3%⁩CRT-025-02ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-03-09⁩V1⁦3⁩ of ⁦3⁩
Detailed design025-D3⁦7%⁩CRT-025-03ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-05-05⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals025-D4⁦7%⁩CRT-025-04ApprovedEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2026-07-01⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation025-D5⁦15%⁩CRT-025-05ApprovedEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2026-08-27⁩V1⁦3⁩ of ⁦3⁩
Structure025-D6⁦12%⁩—SubmittedEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syEng. Wassim Al-Azm⁦2026-10-23⁩V1⁦1⁩ of ⁦3⁩
Finishes025-D7⁦12%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-12-19⁩V0⁦0⁩ of ⁦3⁩
Supply025-D8⁦9%⁩—DraftEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syEng. Wassim Al-Azm⁦2027-02-14⁩V0⁦0⁩ of ⁦3⁩
Installation025-D9⁦9%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-04-12⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning025-D10⁦9%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2027-06-08⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance025-D11⁦7%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2027-08-04⁩V0⁦0⁩ of ⁦3⁩
Final acceptance025-D12⁦6%⁩—DraftEng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.syEng. Wassim Al-Azm⁦2027-09-30⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩