PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
PSA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-10-26⁩
ApprovedCRT-025-05Site works & excavation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-025
Project
Suwayda Drinking-Water Network from Al-Ain Dam
Portfolio
Energy & Water Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Rami Youssef

1The deliverableAuto-filled

DeliverableAuto-filled
Site works & excavation
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Bashir Al-Tai
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦15%⁩
DueAuto-filled
⁦2026-08-27⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-025_3.1_v1.pdfV1Eng. Bashir Al-Tai⁦2026-07-11⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Wassim Al-Azm
Accepted byAuto-filled
Eng. Bashir Al-Tai
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2025-024
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Bashir Al-TaiDeputy President, Local Development & GovernoratesSubmitted—⁦2026-07-11⁩ 09:30
2Evidence against the acceptance criteriaMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-07-12⁩ 11:38
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Bashir Al-TaiProject ownerOn behalf of Eng. Wassim Al-AzmApprovedInspected and accepted against the approved acceptance criteria.⁦2026-07-13⁩ 12:45
4Deliverable matched to the contract lineFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2026-07-15⁩ 10:13
5Certificate linked to the payment certificateFinancial approvalRasha Al-MudarresFinanceApproved—⁦2026-07-16⁩ 11:50

Signatures

Evidence against the acceptance criteria

Mariam Al-Zoubi

Approved⁦2026-07-12⁩

Inspection & technical acceptance — owner

Eng. Bashir Al-Tai

Approved⁦2026-07-13⁩

Deliverable matched to the contract line

Abdullah Al-Ujaili

Approved⁦2026-07-15⁩

Certificate linked to the payment certificate

Rasha Al-Mudarres

Approved⁦2026-07-16⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Bashir Al-Tai on ⁦2026-07-11⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-07-12⁩ at ⁦11:38⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2026-07-13⁩ at ⁦12:45⁩ · On behalf of Eng. Wassim Al-Azm (Eng. Bashir Al-Tai)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-07-15⁩ at ⁦10:13⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2026-07-16⁩ at ⁦11:50⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-07-11⁩

    PRJ-2026-025_3.1_v1.pdf

    Eng. Bashir Al-Tai

Only one version so far.