PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP1B⁦17⁩ elements
Unallocated contingencySYP31.5MSYP 52.5M
Budget at completionSYP1.1BPRJ-2026-025
Weighted progress⁦36%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project722⁦2025-10-12⁩⁦2027-10-04⁩⁦36%⁩1,018.50370.59—
1
Phase177⁦2025-10-12⁩⁦2026-04-07⁩⁦100%⁩61.1161.79—
1.1
WBS element109⁦2025-10-12⁩⁦2026-01-29⁩⁦100%⁩30.5630.890 / 1
1.2
WBS element109⁦2025-12-19⁩⁦2026-04-07⁩⁦100%⁩30.5630.891 / 2
2
Phase177⁦2026-02-25⁩⁦2026-08-21⁩⁦100%⁩122.22123.58—
2.1
WBS element109⁦2026-02-25⁩⁦2026-06-14⁩⁦100%⁩61.1161.791 / 1
2.2
WBS element109⁦2026-05-04⁩⁦2026-08-21⁩⁦100%⁩61.1161.791 / 2
3
Phase210⁦2026-07-11⁩⁦2027-02-06⁩⁦47%⁩387.03185.23—
3.1
WBS element107⁦2026-07-11⁩⁦2026-10-26⁩⁦100%⁩129.01130.441 / 1
3.2
WBS element149⁦2026-07-24⁩⁦2026-12-20⁩⁦42%⁩129.0154.781 / 1
3.3
WBS element76⁦2026-11-22⁩⁦2027-02-06⁩⁦0%⁩129.01—1 / 2
4
Phase172⁦2027-01-09⁩⁦2027-06-30⁩⁦0%⁩305.55——
4.1
WBS element76⁦2027-01-09⁩⁦2027-03-26⁩⁦0%⁩101.85—1 / 1
4.2
WBS element76⁦2027-02-26⁩⁦2027-05-13⁩⁦0%⁩101.85—1 / 1
4.3
WBS element76⁦2027-04-15⁩⁦2027-06-30⁩⁦0%⁩101.85—1 / 2
5
Phase124⁦2027-06-02⁩⁦2027-10-04⁩⁦0%⁩142.59——
5.1
WBS element76⁦2027-06-02⁩⁦2027-08-17⁩⁦0%⁩71.30—1 / 1
5.2
WBS element76⁦2027-07-20⁩⁦2027-10-04⁩⁦0%⁩71.30—1 / 1
Total⁦36%⁩1,018.50370.59