PRJ-2026-025On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

Suwayda Drinking-Water Network from Al-Ain Dam

Add to watchlist

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

Budget (BAC)

SYP 1.1B

Actual cost

SYP 370.6M

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 1B

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-03-16⁩
ApprovedDMD-2026-025Suwayda Drinking-Water Network from Al-Ain Dam

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-025
Project
Suwayda Drinking-Water Network from Al-Ain Dam
Portfolio
Energy & Water Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Rami Youssef

1The proposalAuto-filled

TitleAuto-filled
Suwayda Drinking-Water Network from Al-Ain Dam
Proposed byAuto-filled
Eng. Rami Youssef
DepartmentAuto-filled
Governorate Projects Directorate
Submitted onAuto-filled
⁦2025-03-16⁩
Proposal numberAuto-filled
DMD-2026-025

2Justification

Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.

3Objectives

  1. Rehabilitate core energy, water and transport infrastructure
  2. Comparable public-service quality in every governorate

Strategic objectives served

  • SO-2.1 — Rehabilitate core energy, water and transport infrastructure
  • SO-6.1 — Comparable public-service quality in every governorate

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SYP 1.1B

Funding

The delivering body’s investment-plan allocations

Cost lineAmount
Main contractSYP 755M
Supervision & consultingSYP 147.5M
Internal teamSYP 95M
Contingency reserve (5%)SYP 52.5M
TotalSYP 1.1B

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Rami YoussefDirector, Renewable Energy & Environment ProjectsSubmitted—⁦2025-03-16⁩ 09:06
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2025-03-17⁩ 13:46
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2025-03-20⁩ 14:53
4Portfolio manager reviewTechnical acceptanceEng. Rami YoussefPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-03-23⁩ 09:00
5Cost & funding reviewFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-03-26⁩ 09:42
6Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2025-03-31⁩ 11:14

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2025-03-17⁩

PMO review

Mariam Al-Zoubi

Approved⁦2025-03-20⁩

Portfolio manager review

Eng. Rami Youssef

Approved⁦2025-03-23⁩

Cost & funding review

Rasha Al-Mudarres

Approved⁦2025-03-26⁩

Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2025-03-31⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Rami Youssef on ⁦2025-03-16⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2025-03-17⁩ at ⁦13:46⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-03-20⁩ at ⁦14:53⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2025-03-23⁩ at ⁦09:00⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-03-26⁩ at ⁦09:42⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2025-03-31⁩ at ⁦11:14⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-04-06⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Rami Youssef

  2. V1Returned for edit⁦2025-03-16⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Rami Youssef