Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
- Form no.
- PSA-PMO-F01
- Template edition
- 2.1
- Version
- V2
- Form date
- 2025-03-16
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-025
- Project
- Suwayda Drinking-Water Network from Al-Ain Dam
- Portfolio
- Energy & Water Portfolio
- Sector
- Local Development & Governorates Sector
- Sponsor
- Eng. Bashir Al-Tai
- Project manager
- Eng. Rami Youssef
1The proposalAuto-filled
- TitleAuto-filled
- Suwayda Drinking-Water Network from Al-Ain Dam
- Proposed byAuto-filled
- Eng. Rami Youssef
- DepartmentAuto-filled
- Governorate Projects Directorate
- Submitted onAuto-filled
- 2025-03-16
- Proposal numberAuto-filled
- DMD-2026-025
2Justification
Rehabilitating the trunk lines from Al-Ain dam, the pumping station, the reservoirs and the distribution networks of As-Suwayda city — more water per person and less loss.
3Objectives
- Rehabilitate core energy, water and transport infrastructure
- Comparable public-service quality in every governorate
Strategic objectives served
- SO-2.1 — Rehabilitate core energy, water and transport infrastructure
- SO-6.1 — Comparable public-service quality in every governorate
4Expected benefits
| Kind | Benefit |
|---|---|
| No benefits recorded yet | |
5Cost & feasibility
Estimated cost
SYP 1.1B
Funding
The delivering body’s investment-plan allocations
| Cost line | Amount |
|---|---|
| Main contract | SYP 755M |
| Supervision & consulting | SYP 147.5M |
| Internal team | SYP 95M |
| Contingency reserve (5%) | SYP 52.5M |
| Total | SYP 1.1B |
6Initial risks
| Risk | Level | Proposed response |
|---|---|---|
| No initial risks recorded | ||
Approval logChain: Proposal & feasibility approval · version 4
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Rami YoussefDirector, Renewable Energy & Environment Projects | Submitted | — | 2025-03-16 09:06 |
| 2 | Line manager endorsement | Technical acceptance | Eng. Lina Al-AttarThe requester’s line manager | Approved | — | 2025-03-17 13:46 |
| 3 | PMO review | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2025-03-20 14:53 |
| 4 | Portfolio manager review | Technical acceptance | Eng. Rami YoussefPortfolio manager | Approved | Consistent with the portfolio plan and its priorities. | 2025-03-23 09:00 |
| 5 | Cost & funding review | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2025-03-26 09:42 |
| 6 | Project Approval Committee | Technical acceptance | Dr. Reem Al-QabbaniProject Approval Committee | Approved | — | 2025-03-31 11:14 |
Signatures
Line manager endorsement
Eng. Lina Al-Attar
Approved2025-03-17
PMO review
Mariam Al-Zoubi
Approved2025-03-20
Portfolio manager review
Eng. Rami Youssef
Approved2025-03-23
Cost & funding review
Rasha Al-Mudarres
Approved2025-03-26
Project Approval Committee
Dr. Reem Al-Qabbani
Approved2025-03-31