Execution
Periodic update card
Progress, status, risks and support requested
- Form no.
- PSA-PMO-F07
- Template edition
- 2.2
- Version
- V1
- Form date
- 2026-10-02
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-020
- Project
- Douma Wastewater Treatment Plant
- Portfolio
- Reconstruction & Infrastructure Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Qasem Al-Hariri
1ProgressAuto-filled
From the live data: accepted deliverables, the schedule and finance on the period’s last day.
Actual progress
42%
+3 pts on the last period
Planned to date
52%
SPI
0.81
Actual cost
SYP 3.8B
Main achievements this periodFilled by the project manager
Work went to the approved plan for the period, with the due deliverables handed in.
Prefilled from the August 2026 card — edit it if it changed
2Status
- Overall healthAuto-filled
- Off track
- StageAuto-filled
- Execution
- Forecast finishAuto-filled
- 2027-08-03
The PM’s comment on the statusFilled by the project manager
The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.
Prefilled from the August 2026 card — edit it if it changed
3Risks and impedimentsAuto-filled
4Support requested
What the project needs from leadership or the committeesFilled by the project manager
Approve change request CR-2026-012 for three integration engineers (SYP 24.5M), and the President of the Authority to press the Ministry of Interior on the civil-registry test environment.
Prefilled from the August 2026 card — edit it if it changed
- Includes financial supportAuto-filled
- Yes
Approval logChain: Periodic update approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Qasem Al-HaririDirector, Transport & Housing Projects | Submitted | — | 2026-10-02 09:18 |
| 2 | PMO check | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | The reading agrees with the schedule and finance. | 2026-10-04 11:14 |
| 3 | Sponsor review & approval | Technical acceptance | Salma Al-ZaimProject sponsor | Approved | — | 2026-10-06 12:21 |
Signatures
PMO check
Mariam Al-Zoubi
Approved2026-10-04
Sponsor review & approval
Salma Al-Zaim
Approved2026-10-06