Execution
Periodic update card
Progress, status, risks and support requested
- Form no.
- PSA-PMO-F07
- Template edition
- 2.2
- Version
- V1
- Form date
- 2026-10-02
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-010
- Project
- 20 MW Qalamoun Solar Field
- Portfolio
- Energy & Water Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Rami Youssef
1ProgressAuto-filled
From the live data: accepted deliverables, the schedule and finance on the period’s last day.
Actual progress
55%
+3 pts on the last period
Planned to date
53%
SPI
1.03
Actual cost
SYP 1.3B
Main achievements this periodFilled by the project manager
Work went to the approved plan for the period, with the due deliverables handed in.
Prefilled from the August 2026 card — edit it if it changed
2Status
- Overall healthAuto-filled
- On track
- StageAuto-filled
- Execution
- Forecast finishAuto-filled
- 2027-04-22
The PM’s comment on the statusFilled by the project manager
On track, no material variance from the baseline.
Prefilled from the August 2026 card — edit it if it changed
3Risks and impedimentsAuto-filled
| Code | Risk | Score | Owner |
|---|---|---|---|
| RSK-0041 | Lower world PV prices allow a larger field within the allocation | 12 | Eng. Rami Youssef |
| Code | Impediment | Severity |
|---|---|---|
| No open impediments | ||
4Support requested
What the project needs from leadership or the committeesFilled by the project manager
No support needed this period.
Prefilled from the August 2026 card — edit it if it changed
- Includes financial supportAuto-filled
- No
Approval logChain: Periodic update approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Rami YoussefDirector, Renewable Energy & Environment Projects | Submitted | — | 2026-10-02 14:53 |
| 2 | PMO check | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | The reading agrees with the schedule and finance. | 2026-10-05 12:03 |
| 3 | Sponsor review & approval | Technical acceptance | Salma Al-ZaimProject sponsor | Approved | — | 2026-10-06 13:10 |
Signatures
PMO check
Mariam Al-Zoubi
Approved2026-10-05
Sponsor review & approval
Salma Al-Zaim
Approved2026-10-06