PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026

20 MW Qalamoun Solar Field

PRJ-2026-010 · Development Projects Follow-up Sector · Operational · WP-2025-010

In progressOn track4ExecutionProject manager: Eng. Rami Youssef · Sponsor: Salma Al-Zaim
Progress
⁦58%⁩ / ⁦57%⁩
SPI · CPI
1.02 · 1.01
Spend
SYP 1.4B / SYP 2.4B
Estimate at completion
SYP 2.4B

Schedule

⁦1%⁩ ahead⁦58%⁩

Planned to date ⁦57%⁩

Forecast finish: 2027-04-22 · On time

SPI1.02Schedule performance index · 1.02CPI1.01Cost performance index · 1.01

Health dimensions

On track

Last update: 2026-10-26 · Up to date

Deliverables

⁦7⁩ of ⁦9⁩ due deliverables accepted on time (⁦78%⁩)

Next milestones

  • Testing & acceptance complete2027-03-05
  • Final handover2027-04-30

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SYP 2.4bn: 1 on track and 0 red or critical. Weighted progress is 58% against 57% planned, spend SYP 1.38bn, and EAC SYP 2.38bn (SYP 23.8M under).

No project is more than a month behind baseline.

Planning and Statistics Authority · prepared by Eng. Rami Youssef in MunjazInternal

Status: On track ·Project page