Project status card
28 October 2026
20 MW Qalamoun Solar Field
PRJ-2026-010 · Development Projects Follow-up Sector · Operational · WP-2025-010
- Progress
- 58% / 57%
- SPI · CPI
- 1.02 · 1.01
- Spend
- SYP 1.4B / SYP 2.4B
- Estimate at completion
- SYP 2.4B
Schedule
Planned to date 57%
Forecast finish: 2027-04-22 · On time
SPI1.02Schedule performance index · 1.02CPI1.01Cost performance index · 1.01Health dimensions
Last update: 2026-10-26 · Up to date
Deliverables
7 of 9 due deliverables accepted on time (78%)
Next milestones
- Testing & acceptance complete2027-03-05
- Final handover2027-04-30
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 2.4bn: 1 on track and 0 red or critical. Weighted progress is 58% against 57% planned, spend SYP 1.38bn, and EAC SYP 2.38bn (SYP 23.8M under).
No project is more than a month behind baseline.