PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

e-Litigation & Judicial Notification Platform — Release 2

APPROVEDV2Approved ⁦2025-05-02⁩

1Project identity

Required at this stage
Project name
e-Litigation & Judicial Notification Platform — Release 2
Project code
PRJ-2026-008
Project sponsor
Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy
Project manager
Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy
Project owner
Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy
Portfolio & programme
Digital Government Services & Data PortfolioGovernment e-Services Programme
Type & methodology
Digital · Scrum
Current phase
4Execution

2Background & rationale

Required at this stage

⁦Release 2 of the Ministry of Justice platform⁩: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

3Objectives

Required at this stage
  1. 1Integrated digital government services for citizens
  2. 2Sound governance and effective follow-up of projects and data

4Scope

Required at this stage

In scope

  • ⁦Release 2 of the Ministry of Justice platform⁩: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Identity checks against the civil registry
  2. 2Integration with internal systems
  3. 3Accessibility and UX standards

6Deliverables

Required at this stage
1Project management plan⁦2025-05-27⁩
2Main deliverable — stage 1⁦2026-02-22⁩
3Main deliverable — final stage⁦2026-09-11⁩
4Final report⁦2026-11-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-05-02⁩
  2. Contract signed⁦2025-08-04⁩
  3. 50% of works complete⁦2026-02-22⁩
  4. Provisional acceptance⁦2026-10-15⁩
  5. Closure⁦2026-11-30⁩

8Budget

Required at this stage
  • Main contract⁦71.7%⁩SYP330M
  • Supervision & consulting⁦14.1%⁩SYP65M
  • Internal team⁦9.2%⁩SYP42.5M
  • Contingency reserve (⁦5%⁩)⁦4.9%⁩SYP22.5M
The delivering body’s investment-plan allocationsTotalSYP460M

9Timeline

Required at this stage
Start
2025-05-044 May 2025
Baseline finish
2026-11-3030 November 2026
Duration
⁦19⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly