PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 460M split into spent, committed and left, with the estimate at completion

EAC SYP 451M
Revised request SYP 460M
  • Actual spendSYP 410.4M
  • Committed, not spentSYP 12.1M
  • Allotted, uncommittedSYP 23.7M
  • Contingency availableSYP 13.8M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 427.5M
Original budgetwhen the first baseline was approved
SYP 460M
Approved budgetafter approved change requests
SYP 460M
Current budgetavailable to spend now
SYP 460M
Revised budgetif the pending changes are approved
SYP 460M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 422.5M
Contracts1 active contract
SYP 370M
Purchase orders⁦2⁩ orders
SYP 52.5M
Remaining budgetapproved less actual
SYP 49.6M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 410.4M
Accrualswork done, not yet invoiced
SYP 16.4M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 451M
ContingencySYP 9.2M drawn of SYP 23M
SYP 13.8M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 427.5M
ApprovedSYP 460M
Estimate at completionSYP 451M
Approved is SYP 32.5M (⁦7.6%⁩) above the estimate
The estimate at completion is SYP 23.5M (⁦5.5%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-02-18⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-90008
  • WBS elements⁦5⁩ elements · P-2026-008.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦11⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 9.2M drawn of SYP 23M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 9.2M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance35.7036.0836.0836.08⁦−0.38⁩
2Analysis & design75.8576.6776.6776.67⁦−0.81⁩
3Build178.48180.39180.39180.39⁦−1.91⁩
4Testing & acceptance89.2490.2090.2090.20⁦−0.96⁩
5Launch & handover66.9339.1727.0660.75⁦+6.18⁩
Unallocated contingency13.800.000.006.90⁦+6.90⁩
Total460.00422.50410.39450.98⁦+9.02⁩

Budget split

WBS

SYP 460M

Budget

  • Management & governanceSYP 35.7M⁦8%⁩
  • Analysis & designSYP 75.9M⁦16%⁩
  • BuildSYP 178.5M⁦39%⁩
  • Testing & acceptanceSYP 89.2M⁦19%⁩
  • Launch & handoverSYP 66.9M⁦15%⁩
  • Unallocated contingencySYP 13.8M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-03-02⁩+92

SPI(t) ⁦0.86⁩ against the approved finish ⁦2026-11-30⁩

Planned valuePV
SYP 456.3M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 418.6M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 410.4M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 460M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+8.21⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−37.71⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.02
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.92
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 451M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 40.6M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+9.02⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.83
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 451M
  • If the rest goes to planSYP 451.8M
  • At cost and schedule performanceSYP 454.6M
  • The PM’s bottom-up estimateSYP 451M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 451M

Variance at completion: ⁦+9.02⁩ SYP M