PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-05-29⁩
ApprovedPRJ-2026-008e-Litigation & Judicial Notification Platform — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
e-Litigation & Judicial Notification Platform — Release 2
Portfolio
Digital Government Services & Data Portfolio
Sector
Legal Affairs
Sponsor
Eng. Mustafa Al-Awa
Project manager
Kinan Azzam

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-05-04⁩

Baseline finish

⁦2026-11-30⁩

Forecast finish

⁦2026-11-26⁩

SPI

1.01

MilestonePlannedForecastSlip
Project plan approved⁦2025-09-10⁩⁦2025-09-28⁩+18 days
Designs approved⁦2025-12-18⁩⁦2026-01-19⁩+32 days
Build complete⁦2026-05-16⁩⁦2026-07-07⁩+52 days
Testing & acceptance complete⁦2026-08-23⁩⁦2026-10-26⁩+64 days
Final handover⁦2026-11-30⁩⁦2026-11-30⁩0

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦5%⁩⁦2025-07-22⁩Kinan Azzam
Monitoring & reporting⁦4%⁩⁦2025-09-10⁩Dr. Nisreen Al-Shoufi
Business requirements⁦9%⁩⁦2025-10-29⁩Dr. Nisreen Al-Shoufi
Solution design⁦9%⁩⁦2025-12-18⁩Eng. Mustafa Al-Awa
Release 1⁦14%⁩⁦2026-02-06⁩Eng. Mustafa Al-Awa
Release 2⁦14%⁩⁦2026-03-27⁩Kinan Azzam
Integrations⁦14%⁩⁦2026-05-16⁩Dr. Nisreen Al-Shoufi
System testing⁦11%⁩⁦2026-07-04⁩Kinan Azzam
User acceptance testing⁦11%⁩⁦2026-08-23⁩Dr. Nisreen Al-Shoufi
Training & change⁦5%⁩⁦2026-10-11⁩Dr. Nisreen Al-Shoufi
Go-live & handover⁦4%⁩⁦2026-11-30⁩Eng. Mustafa Al-Awa
Accepted with a certificate⁦91%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyKinan Azzam
Project ownerDeliverable status and acceptance datesFortnightlyKinan Azzam
PMOData and indicator updatesWeeklyKinan Azzam
BeneficiariesWhat changes and whenAt each milestoneKinan Azzam
Team memberRoleAllocation
Kinan AzzamProject manager⁦30%⁩
Eng. Lina Al-AttarProgramme oversight, e-litigation platform⁦15%⁩
Iman Al-JasemMedium-term plan lead on justice-sector indicators⁦10%⁩
—e-Litigation platform to civil registry integration⁦40%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Cases filed and served online0 requests900 requestsDr. Firas Al-Obaid

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Kinan AzzamSenior Digital Delivery Consultant — National PMOSubmitted—⁦2025-05-29⁩ 12:45
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2025-06-03⁩ 14:47
3Technical acceptance — project ownerTechnical acceptanceDr. Nisreen Al-ShoufiProject ownerApproved—⁦2025-06-04⁩ 09:54
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-06-05⁩ 13:40
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-06-09⁩ 14:17
6Sponsor approvalTechnical acceptanceEng. Mustafa Al-AwaProject sponsorApproved—⁦2025-06-10⁩ 12:15

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2025-06-03⁩

Technical acceptance — project owner

Dr. Nisreen Al-Shoufi

Approved⁦2025-06-04⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2025-06-05⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2025-06-09⁩

Sponsor approval

Eng. Mustafa Al-Awa

Approved⁦2025-06-10⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Kinan Azzam on ⁦2025-05-29⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-06-03⁩ at ⁦14:47⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Dr. Nisreen Al-Shoufi · Project owner

    Approved · ⁦2025-06-04⁩ at ⁦09:54⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-06-05⁩ at ⁦13:40⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-06-09⁩ at ⁦14:17⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Mustafa Al-Awa · Project sponsor

    Approved · ⁦2025-06-10⁩ at ⁦12:15⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-05-29⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Kinan Azzam

  2. V1Returned for edit⁦2025-05-15⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Kinan Azzam