e-Litigation & Judicial Notification Platform — Release 2
Add to watchlistRelease 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
Budget (BAC)
Actual cost
89% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
In scope
- Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
- Identity checks against the civil registry
- Integration with internal systems
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2025-06-01
Baseline approved at the planning gate
BudgetSYP460MFinish2026-11-30
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional2
- Technical1
- Regulatory1
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
17%
1/6 · test result is a pass
Accepted
17%
1/6 · signed off by the business owner
Display options
| REQ-008-01 | An end-to-end digital journey, no walk-in | Business | Must | In progress | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | SB-1 | |
| REQ-008-02 | Identity checks against the civil registry | Functional | Must | In progress | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | SB-1 | |
| REQ-008-03 | A user dashboard | Functional | Must | In progress | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | SB-1 | |
| REQ-008-04 | Integration with internal systems | Technical | Could | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | SB-1 | |
| REQ-008-05 | WCAG 2.1 accessibility | Regulatory | Could | In progress | Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy | SB-1 | |
| REQ-008-06 | National cybersecurity controls | Security | Should | In progress | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.