PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice
e-Litigation & Judicial Notification Platform — Release 2
Add to watchlistRelease 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
Project managerKinan AzzamProject sponsorEng. Mustafa Al-AwaProgrammeGovernment e-Services Programme
Budget (BAC)
SYP 460M
Actual cost
SYP 410.4M
89% of budget
Progress
91%Awaiting acceptance 5%
Estimate at completion
SYP 451M
SPI · CPI
1.01Schedule performance index · 1.011.02Cost performance index · 1.02
Forecast finish
2026-11-26
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started