e-Litigation & Judicial Notification Platform — Release 2
Add to watchlistRelease 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
Budget (BAC)
Actual cost
89% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Closure readiness
Closure planned after the forecast finish on 2026-11-26
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Dr. Nisreen Al-ShoufiPlanned 2026-11-16
- 2
Financial closureNot started
Spend reconciled, commitments closed
Omar Al-NahhasPlanned 2026-12-16
- 3
Contract closureNot started
Contracts closed, bonds released
Omar Al-NahhasPlanned 2026-12-26
- 4
Documents archivedNot started
Documents archived with classification
Kinan AzzamPlanned 2026-12-21
- 5
Lessons learnedNot started
Lessons-learned session
Kinan AzzamPlanned 2026-12-11
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Dr. Nisreen Al-ShoufiPlanned 2026-12-06
- 7
Final report approvedNot started
Final report and its approval
Kinan AzzamPlanned 2026-12-31
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2026-11-26), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
- Cases filed and served online
baseline 0 · now 0 · target 900 requests
0% of target realisedHanded over at closure (current owner: Dr. Firas Al-Obaid)