PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2026-11-26⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Dr. Nisreen Al-ShoufiPlanned ⁦2026-11-16⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Omar Al-NahhasPlanned ⁦2026-12-16⁩

  3. 3

    Contract closureNot started

    Contracts closed, bonds released

    Omar Al-NahhasPlanned ⁦2026-12-26⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Kinan AzzamPlanned ⁦2026-12-21⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Kinan AzzamPlanned ⁦2026-12-11⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Dr. Nisreen Al-ShoufiPlanned ⁦2026-12-06⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Kinan AzzamPlanned ⁦2026-12-31⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2026-11-26⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

  • Cases filed and served online

    baseline ⁦0⁩ · now ⁦0⁩ · target ⁦900⁩ requests

    ⁦0%⁩ of target realised
    Handed over at closure (current owner: Dr. Firas Al-Obaid)