PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP446.2M⁦16⁩ elements
Unallocated contingencySYP13.8MSYP 23M
Budget at completionSYP460MPRJ-2026-008
Weighted progress⁦91%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project575⁦2025-05-04⁩⁦2026-11-30⁩⁦91%⁩446.20410.39—
1
Phase147⁦2025-05-04⁩⁦2025-09-28⁩⁦100%⁩35.7036.08—
1.1
WBS element90⁦2025-05-04⁩⁦2025-08-02⁩⁦100%⁩17.8518.040 / 1
1.2
WBS element91⁦2025-06-29⁩⁦2025-09-28⁩⁦100%⁩17.8518.041 / 2
2
Phase147⁦2025-08-25⁩⁦2026-01-19⁩⁦100%⁩75.8576.67—
2.1
WBS element90⁦2025-08-25⁩⁦2025-11-23⁩⁦100%⁩37.9338.331 / 1
2.2
WBS element91⁦2025-10-20⁩⁦2026-01-19⁩⁦100%⁩37.9338.331 / 2
3
Phase203⁦2025-12-16⁩⁦2026-07-07⁩⁦100%⁩178.48180.39—
3.1
WBS element90⁦2025-12-16⁩⁦2026-03-16⁩⁦100%⁩59.4960.131 / 1
3.2
WBS element91⁦2026-02-10⁩⁦2026-05-12⁩⁦100%⁩59.4960.131 / 1
3.3
WBS element90⁦2026-04-08⁩⁦2026-07-07⁩⁦100%⁩59.4960.131 / 2
4
Phase145⁦2026-06-03⁩⁦2026-10-26⁩⁦100%⁩89.2490.20—
4.1
WBS element90⁦2026-06-03⁩⁦2026-09-01⁩⁦100%⁩44.6245.101 / 1
4.2
WBS element88⁦2026-07-30⁩⁦2026-10-26⁩⁦100%⁩44.6245.101 / 2
5
Phase129⁦2026-07-24⁩⁦2026-11-30⁩⁦40%⁩66.9327.06—
5.1
WBS element112⁦2026-07-24⁩⁦2026-11-13⁩⁦80%⁩33.4727.061 / 1
5.2
WBS element21⁦2026-11-05⁩⁦2026-11-26⁩⁦0%⁩33.47—1 / 1
Total⁦91%⁩446.20410.39