PRJ-2026-008On track4ExecutionScrumIn progressDelivered by:Ministry of Justice

e-Litigation & Judicial Notification Platform — Release 2

Add to watchlist

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Budget (BAC)

SYP 460M

Actual cost

SYP 410.4M

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SYP 451M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-05-02⁩
ApprovedPRJ-2026-008e-Litigation & Judicial Notification Platform — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
e-Litigation & Judicial Notification Platform — Release 2
Portfolio
Digital Government Services & Data Portfolio
Sector
Legal Affairs
Sponsor
Eng. Mustafa Al-Awa
Project manager
Kinan Azzam

1Objective

Background

Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.

Project objectives

  1. Integrated digital government services for citizens
  2. Sound governance and effective follow-up of projects and data

2Scope

In scope

  • Release 2 of the Ministry of Justice platform: filing cases, exchanging pleadings and serving judicial notices online and following hearings, linking the courts in the governorate centres.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-05-27⁩
Main deliverable — stage 1⁦2026-02-22⁩
Main deliverable — final stage⁦2026-09-11⁩
Final report⁦2026-11-30⁩
MilestoneDate
Charter approved⁦2025-05-02⁩
Contract signed⁦2025-08-04⁩
50% of works complete⁦2026-02-22⁩
Provisional acceptance⁦2026-10-15⁩
Closure⁦2026-11-30⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Mustafa Al-Awa
Project ownerAuto-filled
Dr. Nisreen Al-Shoufi
Project managerAuto-filled
Kinan Azzam
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 330M
Supervision & consultingSYP 65M
Internal teamSYP 42.5M
Contingency reserve (5%)SYP 22.5M
Approved budgetSYP 460M

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Kinan AzzamSenior Digital Delivery Consultant — National PMOSubmitted—⁦2025-04-23⁩ 10:00
2PMO complianceMethodology reviewDr. Reem Al-QabbaniPMO — directorApproved—⁦2025-04-26⁩ 12:30
3Project ownerTechnical acceptanceDr. Nisreen Al-ShoufiProject ownerApproved—⁦2025-04-29⁩ 09:45
4Budget funding confirmedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-04-30⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Mustafa Al-AwaProject sponsorApproved—⁦2025-05-02⁩ 11:00

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Approved⁦2025-04-26⁩

Project owner

Dr. Nisreen Al-Shoufi

Approved⁦2025-04-29⁩

Budget funding confirmed

Rasha Al-Mudarres

Approved⁦2025-04-30⁩

Sponsor approval

Eng. Mustafa Al-Awa

Approved⁦2025-05-02⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Kinan Azzam on ⁦2025-04-23⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director

    Approved · ⁦2025-04-26⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Dr. Nisreen Al-Shoufi · Project owner

    Approved · ⁦2025-04-29⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-30⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Mustafa Al-Awa · Project sponsor

    Approved · ⁦2025-05-02⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-05-02⁩

    Approved version

    • PMO comments addressed

    Kinan Azzam

  2. V1Returned for edit⁦2025-04-13⁩

    First draft

    • Returned to detail the budget

    Kinan Azzam

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close