Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+91⁩ days vs approved

Baseline (original = approved)⁦2027-03-31⁩
Current forecast⁦2027-06-30⁩
By earned schedule⁦2029-09-27⁩
Critical activities
8
of ⁦10⁩ open activities
Late activities
7
past their baseline finish
Schedule performance
0.42
earned ÷ planned value
Next milestone
in 75 days
Build complete
Expand allCollapse all
Activity
Sheikh Najjar Industrial City RehabilitationPlanned: ⁦2024-09-01⁩ → ⁦2027-03-31⁩Forecast: ⁦2024-09-01⁩ → ⁦2027-06-30⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2024-09-01⁩ → ⁦2025-03-14⁩Actual: ⁦2024-09-01⁩ → ⁦2025-09-02⁩
Project plan & baselinePlanned: ⁦2024-09-01⁩ → ⁦2024-12-29⁩Actual: ⁦2024-09-01⁩ → ⁦2025-04-14⁩
Monitoring & reportingPlanned: ⁦2024-11-15⁩ → ⁦2025-03-14⁩Actual: ⁦2025-01-20⁩ → ⁦2025-09-02⁩
Project plan approvedPlanned: ⁦2025-03-14⁩ → ⁦2025-03-14⁩Actual: ⁦2025-09-02⁩ → ⁦2025-09-02⁩Project plan approved
Design & permitsPlanned: ⁦2025-01-28⁩ → ⁦2025-08-11⁩Actual: ⁦2025-06-09⁩ → ⁦2026-06-10⁩
Detailed designPlanned: ⁦2025-01-28⁩ → ⁦2025-05-28⁩Actual: ⁦2025-06-09⁩ → ⁦2026-01-20⁩
Permits & approvalsPlanned: ⁦2025-04-13⁩ → ⁦2025-08-11⁩Actual: ⁦2025-10-28⁩ → ⁦2026-06-10⁩
Designs approvedPlanned: ⁦2025-08-11⁩ → ⁦2025-08-11⁩Actual: ⁦2026-06-10⁩ → ⁦2026-06-10⁩Designs approved
Civil worksPlanned: ⁦2025-06-27⁩ → ⁦2026-03-23⁩Forecast: ⁦2025-09-09⁩ → ⁦2027-01-11⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2025-06-27⁩ → ⁦2025-10-24⁩Actual: ⁦2026-03-17⁩ → ⁦2026-10-26⁩
StructurePlanned: ⁦2025-09-09⁩ → ⁦2026-01-07⁩Forecast: ⁦2025-09-09⁩ → ⁦2026-12-08⁩Float: ⁦0⁩dDrag to change its duration+335
FinishesPlanned: ⁦2025-11-23⁩ → ⁦2026-03-23⁩Forecast: ⁦2026-11-17⁩ → ⁦2027-01-11⁩Float: ⁦0⁩dDrag to change its dates+294
Build completePlanned: ⁦2026-03-23⁩ → ⁦2026-03-23⁩Forecast: ⁦2027-01-11⁩ → ⁦2027-01-11⁩Float: ⁦170⁩dDrag to change its datesBuild complete
MEP worksPlanned: ⁦2026-02-06⁩ → ⁦2026-11-02⁩Forecast: ⁦2026-12-21⁩ → ⁦2027-04-23⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-02-06⁩ → ⁦2026-06-05⁩Forecast: ⁦2026-12-21⁩ → ⁦2027-02-14⁩Float: ⁦0⁩dDrag to change its dates+254
InstallationPlanned: ⁦2026-04-21⁩ → ⁦2026-08-19⁩Forecast: ⁦2027-01-24⁩ → ⁦2027-03-20⁩Float: ⁦0⁩dDrag to change its dates+213
Testing & commissioningPlanned: ⁦2026-07-05⁩ → ⁦2026-11-02⁩Forecast: ⁦2027-02-27⁩ → ⁦2027-04-23⁩Float: ⁦0⁩dDrag to change its dates+172
Testing & acceptance completePlanned: ⁦2026-11-02⁩ → ⁦2026-11-02⁩Forecast: ⁦2027-04-23⁩ → ⁦2027-04-23⁩Float: ⁦68⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2026-09-18⁩ → ⁦2027-03-31⁩Forecast: ⁦2027-04-02⁩ → ⁦2027-06-30⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-09-18⁩ → ⁦2027-01-15⁩Forecast: ⁦2027-04-02⁩ → ⁦2027-05-27⁩Float: ⁦0⁩dDrag to change its dates+132
Final acceptancePlanned: ⁦2026-12-02⁩ → ⁦2027-03-31⁩Forecast: ⁦2027-05-06⁩ → ⁦2027-06-30⁩Float: ⁦0⁩dDrag to change its dates+91
Final handoverPlanned: ⁦2027-03-31⁩ → ⁦2027-03-31⁩Forecast: ⁦2027-06-30⁩ → ⁦2027-06-30⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦10⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦7⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Structure” needs a pace ⁦5.2⁩× faster than it has kept

It earned ⁦66%⁩ in 414 days; the forecast assumes the rest in 41 days. At the pace so far it finishes on ⁦2027-05-29⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 235 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

172
303
294
172
G1G2G3G4

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close