PRJ-2026-006Off track4ExecutionConstructionStalledDelivered by:Ministry of Industry, Internal Trade and Consumer Protection

Sheikh Najjar Industrial City Rehabilitation

Remove from watchlist

Rehabilitating Sheikh Najjar Industrial City’s infrastructure — internal roads, water and drainage networks, power stations and ground improvement on damaged plots — so factories can resume production.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 7.2B

Actual cost

SYP 3.1B

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SYP 8B

+SYP 883.7M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
PSA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2024-09-08⁩
ApprovedMTG-KO-006Kick-off — Sheikh Najjar Industrial City Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Sheikh Najjar Industrial City Rehabilitation
Portfolio
Health, Education & Industrial Recovery Portfolio
Sector
Local Development & Governorates Sector
Sponsor
Eng. Bashir Al-Tai
Project manager
Eng. Youssef Shehabi

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Sheikh Najjar Industrial City Rehabilitation
Date and timeAuto-filled
⁦2024-09-08⁩ · 10:00
PlaceAuto-filled
Main meeting room — Authority HQ, Kafr Sousa
SecretaryAuto-filled
Eng. Youssef Shehabi

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Bashir Al-TaiDeputy President, Local Development & Governorates
Eng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction Projects
Eng. Youssef ShehabiSenior Project Manager — Governorate Projects
Dr. Reem Al-QabbaniDirector, National Project Management Office
Eng. Fadi Al-DroubiDirector General, Human Development Projects

2Roles

PersonRoleDuty
Eng. Bashir Al-TaiProject sponsorSponsors the project, decides escalations and material changes
Eng. Wassim Al-AzmProject ownerApproves the requirements and accepts the deliverables
Eng. Youssef ShehabiProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Reem Al-QabbaniProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Fadi Al-DroubiHuman-development lead on industrial workforce programmesDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Youssef Shehabi⁦2025-03-14⁩Done
Designs approvedEng. Youssef Shehabi⁦2025-08-11⁩Done
Build completeEng. Youssef Shehabi⁦2026-03-23⁩Open
Testing & acceptance completeEng. Youssef Shehabi⁦2026-11-02⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-01-30⁩
Start confirmed
Eng. Bashir Al-Tai · ⁦2024-09-09⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Youssef ShehabiSenior Project Manager — Governorate ProjectsSubmitted—⁦2024-09-09⁩ 11:56
2Minutes against the templateMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-09-10⁩ 09:00
3Chair’s approval (sponsor)Technical acceptanceEng. Bashir Al-TaiProject sponsorApproved—⁦2024-09-10⁩ 12:30

Signatures

Minutes against the template

Mariam Al-Zoubi

Approved⁦2024-09-10⁩

Chair’s approval (sponsor)

Eng. Bashir Al-Tai

Approved⁦2024-09-10⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Youssef Shehabi on ⁦2024-09-09⁩

  1. Methodology review

    Minutes against the template

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-09-10⁩ at ⁦09:00⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Bashir Al-Tai · Project sponsor

    Approved · ⁦2024-09-10⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-09-08⁩