PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
PSA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2024-01-21⁩
ApprovedMTG-KO-004Kick-off — Aleppo 230 kV Substations Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Aleppo 230 kV Substations Rehabilitation
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Aleppo 230 kV Substations Rehabilitation
Date and timeAuto-filled
⁦2024-01-21⁩ · 10:00
PlaceAuto-filled
Main meeting room — Authority HQ, Kafr Sousa
SecretaryAuto-filled
Eng. Maher Al-Hamawi

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Salma Al-ZaimDeputy President, Finance, Administration & the Investment Plan
Eng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction Projects
Eng. Maher Al-HamawiDirector, Energy, Water & Utilities Projects
Dr. Reem Al-QabbaniDirector, National Project Management Office
Eng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-up
Huda Al-DandalSenior Financial Analyst — Investment Plan
——

2Roles

PersonRoleDuty
Salma Al-ZaimProject sponsorSponsors the project, decides escalations and material changes
Eng. Wassim Al-AzmProject ownerApproves the requirements and accepts the deliverables
Eng. Maher Al-HamawiProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Reem Al-QabbaniProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Abdulrahman Al-KilaniFollow-up lead — substations’ readiness to energiseDelivers their tasks and uploads the evidence
Huda Al-DandalFinancial analystDelivers their tasks and uploads the evidence
—Contractor’s site managerDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Maher Al-Hamawi⁦2024-08-05⁩Done
Designs approvedEng. Maher Al-Hamawi⁦2025-01-09⁩Done
Build completeEng. Maher Al-Hamawi⁦2025-09-02⁩Done
Testing & acceptance completeEng. Maher Al-Hamawi⁦2026-04-26⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. Project Approval Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2024-06-20⁩
Start confirmed
Salma Al-Zaim · ⁦2024-01-22⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2024-01-22⁩ 09:42
2Chair’s approval (sponsor)Technical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2024-01-23⁩ 12:30
3Minutes against the templateMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2024-01-23⁩ 13:46

Signatures

Minutes against the template

Mariam Al-Zoubi

Approved⁦2024-01-23⁩

Chair’s approval (sponsor)

Salma Al-Zaim

Approved⁦2024-01-23⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2024-01-22⁩

  1. Methodology review

    Minutes against the template

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-01-23⁩ at ⁦13:46⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2024-01-23⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-01-21⁩

    The minutes as taken

    Eng. Maher Al-Hamawi

Only one version so far.