PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
PSA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2023-08-12⁩
ApprovedPRJ-2026-004Aleppo 230 kV Substations Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Aleppo 230 kV Substations Rehabilitation
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1The resultAuto-filled

Priority score

87 of 100

Class

P1

75–100

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the development framework⁦20%⁩5.020.0
Development value⁦12%⁩5.012.0
Economic & social return⁦8%⁩5.08.0
Urgency⁦10%⁩5.010.0
Legal requirement⁦10%⁩1.61.5
Risk⁦7%⁩1.36.5
Complexity⁦6%⁩1.65.1
Resource requirement⁦5%⁩1.93.9
Impact on citizens & beneficiaries⁦14%⁩5.014.0
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩4.94.9
Total⁦100%⁩—87

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2023-08-12⁩ 13:10
2Evaluation checked against the modelMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2023-08-13⁩ 11:14
3Portfolio manager reviewTechnical acceptanceEng. Rami YoussefPortfolio managerApproved—⁦2023-08-15⁩ 12:21
4Class approved — Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2023-08-21⁩ 08:00
5Class approved — Project Approval CommitteeTechnical acceptanceDr. Reem Al-QabbaniProject Approval CommitteeApproved—⁦2023-08-22⁩ 13:28

Signatures

Evaluation checked against the model

Mariam Al-Zoubi

Approved⁦2023-08-13⁩

Portfolio manager review

Eng. Rami Youssef

Approved⁦2023-08-15⁩

Class approved — Project Approval Committee

Dr. Reem Al-Qabbani

Approved⁦2023-08-22⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2023-08-12⁩

  1. Methodology review

    Evaluation checked against the model

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2023-08-13⁩ at ⁦11:14⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Rami Youssef · Portfolio manager

    Approved · ⁦2023-08-15⁩ at ⁦12:21⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Approved · ⁦2023-08-22⁩ at ⁦13:28⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2023-08-12⁩

    Evaluated on the approved priority model

    Mariam Al-Zoubi

Only one version so far.