PSA/2024/017
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 210M — if approved the value becomes SYP 7.7B
43% of the current value paid
Paid
SYP3.2Bof a current value of SYP 7.5B
Value of each certificate
The last 14 — gross and net
Approved: 18
Count: 18 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 18September 2026 | 2026-10-05 | SYP162.5M | SYP16.3M | SYP16.3M | SYP130M | Approved | |
| Certificate 17August 2026 | 2026-09-03 | SYP78M | SYP7.8M | SYP7.8M | SYP62.4M | Approved | |
| Certificate 16June 2026 | 2026-07-18 | SYP113.3M | SYP11.3M | SYP11.3M | SYP90.6M | Approved | |
| Certificate 15May 2026 | 2026-06-01 | SYP152.5M | SYP15.3M | SYP15.3M | SYP122M | Approved | |
| Certificate 14March 2026 | 2026-04-16 | SYP156.3M | SYP15.6M | SYP15.6M | SYP125M | Approved | |
| Certificate 13February 2026 | 2026-02-28 | SYP209.8M | SYP21M | SYP21M | SYP167.8M | Approved | |
| Certificate 12December 2025 | 2026-01-12 | SYP221.3M | SYP22.1M | SYP22.1M | SYP177M | Approved | |
| Certificate 11November 2025 | 2025-11-26 | SYP210.8M | SYP21.1M | SYP21.1M | SYP168.6M | Approved | |
| Certificate 10September 2025 | 2025-10-10 | SYP267M | SYP26.7M | SYP26.7M | SYP213.6M | Approved | |
| Certificate 9August 2025 | 2025-08-25 | SYP232.8M | SYP23.3M | SYP23.3M | SYP186.2M | Approved | |
| Certificate 8June 2025 | 2025-07-09 | SYP231.3M | SYP23.1M | SYP23.1M | SYP185M | Approved | |
| Certificate 7May 2025 | 2025-05-23 | SYP256M | SYP25.6M | SYP25.6M | SYP204.8M | Approved | |
| Certificate 6March 2025 | 2025-04-06 | SYP197M | SYP19.7M | SYP19.7M | SYP157.6M | Approved | |
| Certificate 5January 2025 | 2025-02-18 | SYP201.8M | SYP20.2M | SYP20.2M | SYP161.4M | Approved | |
| Certificate 4December 2024 | 2025-01-02 | SYP182M | SYP18.2M | SYP18.2M | SYP145.6M | Approved | |
| Certificate 3October 2024 | 2024-11-17 | SYP132M | SYP13.2M | SYP13.2M | SYP105.6M | Approved | |
| Certificate 2September 2024 | 2024-10-01 | SYP118.5M | SYP11.9M | SYP11.9M | SYP94.8M | Approved | |
| Certificate 1July 2024 | 2024-08-15 | SYP80M | SYP8M | SYP8M | SYP64M | Approved |