Certificate ⁦8⁩ — June 2025

Douma wastewater treatment plant — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
8
Date
⁦2025-07-09⁩
Reference
PAY-2024-017-08

Interim payment certificate no. (⁦8⁩)

For the work of June 2025

Contract number
PSA/2024/017
Tender file no.
2402200225
Contract
Douma wastewater treatment plant — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
SYP7,450,000,000
Current contract value
SYP7,450,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date1,398,500,000
2Less: previous certificates(1,167,250,000)
3Value of work in this certificate231,250,000
4Less: retention (⁦10%⁩)(23,125,000)
5Less: advance payment recovery (⁦10%⁩)(23,125,000)
6Less: delay and breach penalties0
7Total deductions(46,250,000)
8Net amount payable to the contractorSYP185,000,000

Amount in words: One hundred eighty-five million Syrian pounds only

Retention held up to this certificate: SYP 139.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation521,500,000190,425,00035,425,000225,850,000⁦43%⁩
Earthworks & foundations1,341,000,000296,350,00056,075,000352,425,000⁦26%⁩
Concrete & structural works2,309,500,000397,825,00079,075,000476,900,000⁦21%⁩
Mechanical, electrical & plumbing1,788,000,000193,900,00041,050,000234,950,000⁦13%⁩
Finishes & external works1,117,500,00077,375,00017,025,00094,400,000⁦8%⁩
Testing & commissioning372,500,00011,375,0002,600,00013,975,000⁦4%⁩
Total7,450,000,0001,167,250,000231,250,0001,398,500,000⁦19%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-07-09⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-07-11⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2025-07-14⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-07-17⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-07-20⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-07-09⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-07-11⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-07-14⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2025-07-17⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-20⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

20 July 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-07-20 13:00

17 July 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-07-17 13:00

14 July 2025

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2025-07-14 13:00

11 July 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”