Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 17
- Date
- 2026-09-03
- Reference
- PAY-2024-017-17
Interim payment certificate no. (17)
For the work of August 2026
- Contract number
- PSA/2024/017
- Tender file no.
- 2402200225
- Contract
- Douma wastewater treatment plant — construction
- Contractor
- Al-Bunyan Al-Mateen Contracting Co.
- Contractor tax number
- TX-403137
- Project
- Douma Wastewater Treatment Plant
- Contract period
- 2024-07-01 — 2027-05-31
- Original contract value
- SYP7,450,000,000
- Current contract value
- SYP7,450,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 3,040,000,000 |
| 2 | Less: previous certificates | (2,962,000,000) |
| 3 | Value of work in this certificate | 78,000,000 |
| 4 | Less: retention (10%) | (7,800,000) |
| 5 | Less: advance payment recovery (10%) | (7,800,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (15,600,000) |
| 8 | Net amount payable to the contractor | SYP62,400,000 |
Amount in words: Sixty-two million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 304M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 521,500,000 | 480,050,000 | 10,900,000 | 490,950,000 | 94% |
| Earthworks & foundations | 1,341,000,000 | 748,375,000 | 17,700,000 | 766,075,000 | 57% |
| Concrete & structural works | 2,309,500,000 | 1,009,850,000 | 26,800,000 | 1,036,650,000 | 45% |
| Mechanical, electrical & plumbing | 1,788,000,000 | 495,650,000 | 15,075,000 | 510,725,000 | 29% |
| Finishes & external works | 1,117,500,000 | 198,675,000 | 6,525,000 | 205,200,000 | 18% |
| Testing & commissioning | 372,500,000 | 29,400,000 | 1,000,000 | 30,400,000 | 8% |
| Total | 7,450,000,000 | 2,962,000,000 | 78,000,000 | 3,040,000,000 | 41% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Anas Al-Sheikh
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Qasem Al-Hariri
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar