Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦16⁩ — June 2026

Douma wastewater treatment plant — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
16
Date
⁦2026-07-18⁩
Reference
PAY-2024-017-16

Interim payment certificate no. (⁦16⁩)

For the work of June 2026

Contract number
PSA/2024/017
Tender file no.
2402200225
Contract
Douma wastewater treatment plant — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
SYP7,450,000,000
Current contract value
SYP7,450,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date2,962,000,000
2Less: previous certificates(2,848,750,000)
3Value of work in this certificate113,250,000
4Less: retention (⁦10%⁩)(11,325,000)
5Less: advance payment recovery (⁦10%⁩)(11,325,000)
6Less: delay and breach penalties0
7Total deductions(22,650,000)
8Net amount payable to the contractorSYP90,600,000

Amount in words: Ninety million six hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 296.2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation521,500,000462,450,00015,900,000478,350,000⁦92%⁩
Earthworks & foundations1,341,000,000720,625,00025,800,000746,425,000⁦56%⁩
Concrete & structural works2,309,500,000971,175,00038,875,0001,010,050,000⁦44%⁩
Mechanical, electrical & plumbing1,788,000,000475,850,00021,775,000497,625,000⁦28%⁩
Finishes & external works1,117,500,000190,525,0009,400,000199,925,000⁦18%⁩
Testing & commissioning372,500,00028,125,0001,500,00029,625,000⁦8%⁩
Total7,450,000,0002,848,750,000113,250,0002,962,000,000⁦40%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2026-07-18⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-07-20⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2026-07-23⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-07-26⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-07-29⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-18⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2026-07-20⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-07-23⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2026-07-26⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-29⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

29 July 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-07-29 13:00

26 July 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-07-26 13:00

23 July 2026

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2026-07-23 13:00

20 July 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-07-20 13:00

18 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-18 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close