Certificate ⁦9⁩ — August 2025

Douma wastewater treatment plant — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
9
Date
⁦2025-08-25⁩
Reference
PAY-2024-017-09

Interim payment certificate no. (⁦9⁩)

For the work of August 2025

Contract number
PSA/2024/017
Tender file no.
2402200225
Contract
Douma wastewater treatment plant — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
SYP7,450,000,000
Current contract value
SYP7,450,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date1,631,250,000
2Less: previous certificates(1,398,500,000)
3Value of work in this certificate232,750,000
4Less: retention (⁦10%⁩)(23,275,000)
5Less: advance payment recovery (⁦10%⁩)(23,275,000)
6Less: delay and breach penalties0
7Total deductions(46,550,000)
8Net amount payable to the contractorSYP186,200,000

Amount in words: One hundred eighty-six million two hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 163.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation521,500,000228,175,00035,275,000263,450,000⁦51%⁩
Earthworks & foundations1,341,000,000355,075,00056,000,000411,075,000⁦31%⁩
Concrete & structural works2,309,500,000476,625,00079,625,000556,250,000⁦24%⁩
Mechanical, electrical & plumbing1,788,000,000232,300,00041,750,000274,050,000⁦15%⁩
Finishes & external works1,117,500,00092,700,00017,400,000110,100,000⁦10%⁩
Testing & commissioning372,500,00013,625,0002,700,00016,325,000⁦4%⁩
Total7,450,000,0001,398,500,000232,750,0001,631,250,000⁦22%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-08-25⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-08-27⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2025-08-30⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-09-02⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-09-05⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-08-25⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-08-27⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-08-30⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2025-09-02⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-09-05⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

5 September 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-09-05 13:00

2 September 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-09-02 13:00

30 August 2025

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2025-08-30 13:00

27 August 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-08-27 13:00

25 August 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-08-25 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close