Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦1⁩ — July 2024

Douma wastewater treatment plant — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
1
Date
⁦2024-08-15⁩
Reference
PAY-2024-017-01

Interim payment certificate no. (⁦1⁩)

For the work of July 2024

Contract number
PSA/2024/017
Tender file no.
2402200225
Contract
Douma wastewater treatment plant — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
SYP7,450,000,000
Current contract value
SYP7,450,000,000
Linked milestone
Site handover & mobilisation · MS-G1 Project plan approved

Certificate summary (SYP)

1Total value of work completed to date80,000,000
2Less: previous certificates0
3Value of work in this certificate80,000,000
4Less: retention (⁦10%⁩)(8,000,000)
5Less: advance payment recovery (⁦10%⁩)(8,000,000)
6Less: delay and breach penalties0
7Total deductions(16,000,000)
8Net amount payable to the contractorSYP64,000,000

Amount in words: Sixty-four million Syrian pounds only

Retention held up to this certificate: SYP 8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation521,500,000012,925,00012,925,000⁦2%⁩
Earthworks & foundations1,341,000,000020,150,00020,150,000⁦2%⁩
Concrete & structural works2,309,500,000027,275,00027,275,000⁦1%⁩
Mechanical, electrical & plumbing1,788,000,000013,450,00013,450,000⁦1%⁩
Finishes & external works1,117,500,00005,400,0005,400,000⁦0%⁩
Testing & commissioning372,500,0000800,000800,000⁦0%⁩
Total7,450,000,000080,000,00080,000,000⁦1%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2024-08-15⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2024-08-17⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2024-08-20⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2024-08-23⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2024-08-26⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-08-15⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2024-08-17⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2024-08-20⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2024-08-23⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-08-26⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSite handover & mobilisationDone · ⁦2024-09-03⁩
  2. Project milestoneMS-G1Project plan approvedMilestone approved ⁦2025-05-14⁩1 evidence file

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

26 August 2024

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2024-08-26 13:00

23 August 2024

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2024-08-23 13:00

20 August 2024

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2024-08-20 13:00

17 August 2024

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2024-08-17 13:00

15 August 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-08-15 09:00