Certificate ⁦2⁩ — September 2024

Douma wastewater treatment plant — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
2
Date
⁦2024-10-01⁩
Reference
PAY-2024-017-02

Interim payment certificate no. (⁦2⁩)

For the work of September 2024

Contract number
PSA/2024/017
Tender file no.
2402200225
Contract
Douma wastewater treatment plant — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
SYP7,450,000,000
Current contract value
SYP7,450,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date198,500,000
2Less: previous certificates(80,000,000)
3Value of work in this certificate118,500,000
4Less: retention (⁦10%⁩)(11,850,000)
5Less: advance payment recovery (⁦10%⁩)(11,850,000)
6Less: delay and breach penalties0
7Total deductions(23,700,000)
8Net amount payable to the contractorSYP94,800,000

Amount in words: Ninety-four million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 19.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation521,500,00013,050,00019,000,00032,050,000⁦6%⁩
Earthworks & foundations1,341,000,00020,300,00029,725,00050,025,000⁦4%⁩
Concrete & structural works2,309,500,00027,275,00040,425,00067,700,000⁦3%⁩
Mechanical, electrical & plumbing1,788,000,00013,300,00020,050,00033,350,000⁦2%⁩
Finishes & external works1,117,500,0005,300,0008,100,00013,400,000⁦1%⁩
Testing & commissioning372,500,000775,0001,200,0001,975,000⁦1%⁩
Total7,450,000,00080,000,000118,500,000198,500,000⁦3%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2024-10-01⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2024-10-03⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2024-10-06⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2024-10-09⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2024-10-12⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-10-01⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2024-10-03⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2024-10-06⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2024-10-09⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-10-12⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-04-25⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-02-03⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

12 October 2024

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2024-10-12 13:00

9 October 2024

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2024-10-09 13:00

6 October 2024

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2024-10-06 13:00

3 October 2024

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2024-10-03 13:00

1 October 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-10-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close