Douma Wastewater Treatment Plant
Remove from watchlistA wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
+SYP 453.9M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-01-14 | 2025-05-14 | +120 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-07-06 | 2026-02-03 | +212 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-23 | 2027-03-09 | +351 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-12-09 | 2027-06-04 | +177 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-05-31 | 2027-08-01 | +62 days | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
44%Awaiting acceptance
12%Not handed in
44%Deliverable flow
Display options
| Project plan & baseline020-D1 | 3% | CRT-020-01 | Approved | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Jwan Othman | 2024-10-19 | V1 | 3 of 3 |
| Monitoring & reporting020-D2 | 3% | CRT-020-02 | Approved | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | Jwan Othman | 2025-01-14 | V1 | 3 of 3 |
| Detailed design020-D3 | 6% | CRT-020-03 | Approved | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | Jwan Othman | 2025-04-10 | V1 | 3 of 3 |
| Permits & approvals020-D4 | 6% | CRT-020-04 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Jwan Othman | 2025-07-06 | V1 | 3 of 3 |
| Site works & excavation020-D5 | 13% | CRT-020-05 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Jwan Othman | 2025-10-01 | V1 | 3 of 3 |
| Structure020-D6 | 13% | CRT-020-06 | Approved | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Jwan Othman | 2025-12-27 | V1 | 3 of 3 |
| Finishes020-D7 | 12% | — | Submitted | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | Jwan Othman | 2026-03-23 | V1 | 1 of 3 |
| Supply020-D8 | 10% | — | Draft | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | Jwan Othman | 2026-06-18 | V0 | 0 of 3 |
| Installation020-D9 | 10% | — | Draft | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | Jwan Othman | 2026-09-13 | V0 | 0 of 3 |
| Testing & commissioning020-D10 | 10% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Jwan Othman | 2026-12-09 | V0 | 0 of 3 |
| Provisional acceptance020-D11 | 7% | — | Draft | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | Jwan Othman | 2027-03-05 | V0 | 0 of 3 |
| Final acceptance020-D12 | 7% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Jwan Othman | 2027-05-31 | V0 | 0 of 3 |
| Total · 12 | 100% |