Certificate ⁦4⁩ — December 2024

Douma wastewater treatment plant — construction

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
4
Date
⁦2025-01-02⁩
Reference
PAY-2024-017-04

Interim payment certificate no. (⁦4⁩)

For the work of December 2024

Contract number
PSA/2024/017
Tender file no.
2402200225
Contract
Douma wastewater treatment plant — construction
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
SYP7,450,000,000
Current contract value
SYP7,450,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date512,500,000
2Less: previous certificates(330,500,000)
3Value of work in this certificate182,000,000
4Less: retention (⁦10%⁩)(18,200,000)
5Less: advance payment recovery (⁦10%⁩)(18,200,000)
6Less: delay and breach penalties0
7Total deductions(36,400,000)
8Net amount payable to the contractorSYP145,600,000

Amount in words: One hundred forty-five million six hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 51.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation521,500,00053,875,00028,875,00082,750,000⁦16%⁩
Earthworks & foundations1,341,000,00083,875,00045,275,000129,150,000⁦10%⁩
Concrete & structural works2,309,500,000112,650,00062,125,000174,775,000⁦8%⁩
Mechanical, electrical & plumbing1,788,000,00054,950,00031,150,00086,100,000⁦5%⁩
Finishes & external works1,117,500,00021,950,00012,650,00034,600,000⁦3%⁩
Testing & commissioning372,500,0003,200,0001,925,0005,125,000⁦1%⁩
Total7,450,000,000330,500,000182,000,000512,500,000⁦7%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-01-02⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-01-04⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2025-01-07⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-01-10⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-01-13⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-01-02⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-01-04⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-01-07⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2025-01-10⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-01-13⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-04-25⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-02-03⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Dr. Samer Al-Daqqar

Certificate history

13 January 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-01-13 13:00

10 January 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-01-10 13:00

7 January 2025

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2025-01-07 13:00

4 January 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-01-04 13:00

2 January 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-01-02 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close