Open claims: 3; pending variations worth SYP 95M. A settlement session with the contractor is advised before deciding the next certificate.
Confidence84%
PSA/2024/003
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 95M — if approved the value becomes SYP 9.4B
72% of the current value paid
Paid
SYP6.7Bof a current value of SYP 9.3B
AI insight
Open claims: 3; pending variations worth SYP 95M. A settlement session with the contractor is advised before deciding the next certificate.
Value of each certificate
The last 14 — gross and net
Approved: 32
Count: 33 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 33September 2026 | 2026-10-08 | SYP135M | SYP13.5M | SYP23M | SYP98.5M | Returned | |
| Certificate 32August 2026 | 2026-09-09 | SYP177.5M | SYP17.8M | SYP17.8M | SYP142M | Approved | |
| Certificate 31July 2026 | 2026-08-06 | SYP155M | SYP15.5M | SYP15.5M | SYP124M | Approved | |
| Certificate 30June 2026 | 2026-07-05 | SYP86M | SYP8.6M | SYP8.6M | SYP68.8M | Approved | |
| Certificate 29May 2026 | 2026-06-06 | SYP114.3M | SYP11.4M | SYP11.4M | SYP91.4M | Approved | |
| Certificate 28April 2026 | 2026-05-08 | SYP125.8M | SYP12.6M | SYP12.6M | SYP100.6M | Approved | |
| Certificate 27March 2026 | 2026-04-09 | SYP151.5M | SYP15.2M | SYP15.2M | SYP121.2M | Approved | |
| Certificate 26February 2026 | 2026-03-11 | SYP185.5M | SYP18.6M | SYP18.6M | SYP148.4M | Approved | |
| Certificate 25January 2026 | 2026-02-10 | SYP175.8M | SYP17.6M | SYP17.6M | SYP140.6M | Approved | |
| Certificate 24December 2025 | 2026-01-12 | SYP221.3M | SYP22.1M | SYP22.1M | SYP177M | Approved | |
| Certificate 23November 2025 | 2025-12-14 | SYP235.8M | SYP23.6M | SYP23.6M | SYP188.6M | Approved | |
| Certificate 22October 2025 | 2025-11-15 | SYP220M | SYP22M | SYP22M | SYP176M | Approved | |
| Certificate 21September 2025 | 2025-10-17 | SYP281M | SYP28.1M | SYP28.1M | SYP224.8M | Approved | |
| Certificate 20August 2025 | 2025-09-18 | SYP259.8M | SYP26M | SYP26M | SYP207.8M | Approved | |
| Certificate 19July 2025 | 2025-08-20 | SYP261M | SYP26.1M | SYP26.1M | SYP208.8M | Approved | |
| Certificate 18July 2025 | 2025-07-22 | SYP314.8M | SYP31.5M | SYP31.5M | SYP251.8M | Approved | |
| Certificate 17June 2025 | 2025-06-23 | SYP263.8M | SYP26.4M | SYP26.4M | SYP211M | Approved | |
| Certificate 16May 2025 | 2025-05-25 | SYP293M | SYP29.3M | SYP29.3M | SYP234.4M | Approved | |
| Certificate 15April 2025 | 2025-04-27 | SYP313.8M | SYP31.4M | SYP31.4M | SYP251M | Approved | |
| Certificate 14March 2025 | 2025-03-29 | SYP256.8M | SYP25.7M | SYP25.7M | SYP205.4M | Approved | |
| Certificate 13February 2025 | 2025-02-28 | SYP303.5M | SYP30.4M | SYP30.4M | SYP242.8M | Approved | |
| Certificate 12January 2025 | 2025-01-30 | SYP282M | SYP28.2M | SYP28.2M | SYP225.6M | Approved | |
| Certificate 11December 2024 | 2025-01-01 | SYP243.5M | SYP24.4M | SYP24.4M | SYP194.8M | Approved | |
| Certificate 10November 2024 | 2024-12-03 | SYP282.5M | SYP28.3M | SYP28.3M | SYP226M | Approved | |
| Certificate 9October 2024 | 2024-11-04 | SYP232.3M | SYP23.2M | SYP23.2M | SYP185.8M | Approved | |
| Certificate 8September 2024 | 2024-10-06 | SYP219.5M | SYP22M | SYP22M | SYP175.6M | Approved | |
| Certificate 7August 2024 | 2024-09-07 | SYP230.5M | SYP23.1M | SYP23.1M | SYP184.4M | Approved | |
| Certificate 6July 2024 | 2024-08-09 | SYP177.8M | SYP17.8M | SYP17.8M | SYP142.2M | Approved | |
| Certificate 5June 2024 | 2024-07-11 | SYP176.8M | SYP17.7M | SYP17.7M | SYP141.4M | Approved | |
| Certificate 4May 2024 | 2024-06-12 | SYP159.5M | SYP16M | SYP16M | SYP127.6M | Approved | |
| Certificate 3April 2024 | 2024-05-14 | SYP123M | SYP12.3M | SYP12.3M | SYP98.4M | Approved | |
| Certificate 2March 2024 | 2024-04-15 | SYP113M | SYP11.3M | SYP11.3M | SYP90.4M | Approved | |
| Certificate 1February 2024 | 2024-03-17 | SYP86.8M | SYP8.7M | SYP8.7M | SYP69.4M | Approved |