Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 7
- Date
- 2024-09-07
- Reference
- PAY-2024-003-07
Interim payment certificate no. (7)
For the work of August 2024
- Contract number
- PSA/2024/003
- Tender file no.
- 2401220043
- Contract
- Aleppo 230 kV substations — supply, installation & civil works
- Contractor
- Al-Shahbaa Construction & Rehabilitation Co.
- Contractor tax number
- TX-415685
- Project
- Aleppo 230 kV Substations Rehabilitation
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- SYP8,800,000,000
- Current contract value
- SYP9,335,000,000including variations of SYP 535M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,067,250,000 |
| 2 | Less: previous certificates | (836,750,000) |
| 3 | Value of work in this certificate | 230,500,000 |
| 4 | Less: retention (10%) | (23,050,000) |
| 5 | Less: advance payment recovery (10%) | (23,050,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (46,100,000) |
| 8 | Net amount payable to the contractor | SYP184,400,000 |
Amount in words: One hundred eighty-four million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 106.7M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 653,450,000 | 136,225,000 | 36,125,000 | 172,350,000 | 26% |
| Earthworks & foundations | 1,680,300,000 | 212,125,000 | 56,825,000 | 268,950,000 | 16% |
| Concrete & structural works | 2,893,850,000 | 285,200,000 | 78,725,000 | 363,925,000 | 13% |
| Mechanical, electrical & plumbing | 2,240,400,000 | 139,300,000 | 40,000,000 | 179,300,000 | 8% |
| Finishes & external works | 1,400,250,000 | 55,675,000 | 16,375,000 | 72,050,000 | 5% |
| Testing & commissioning | 466,750,000 | 8,225,000 | 2,450,000 | 10,675,000 | 2% |
| Total | 9,335,000,000 | 836,750,000 | 230,500,000 | 1,067,250,000 | 11% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Karim Al-Ibrahim
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Maher Al-Hamawi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar