Certificate ⁦7⁩ — August 2024

Aleppo 230 kV substations — supply, installation & civil works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
7
Date
⁦2024-09-07⁩
Reference
PAY-2024-003-07

Interim payment certificate no. (⁦7⁩)

For the work of August 2024

Contract number
PSA/2024/003
Tender file no.
2401220043
Contract
Aleppo 230 kV substations — supply, installation & civil works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Aleppo 230 kV Substations Rehabilitation
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
SYP8,800,000,000
Current contract value
SYP9,335,000,000including variations of SYP 535M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date1,067,250,000
2Less: previous certificates(836,750,000)
3Value of work in this certificate230,500,000
4Less: retention (⁦10%⁩)(23,050,000)
5Less: advance payment recovery (⁦10%⁩)(23,050,000)
6Less: delay and breach penalties0
7Total deductions(46,100,000)
8Net amount payable to the contractorSYP184,400,000

Amount in words: One hundred eighty-four million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 106.7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation653,450,000136,225,00036,125,000172,350,000⁦26%⁩
Earthworks & foundations1,680,300,000212,125,00056,825,000268,950,000⁦16%⁩
Concrete & structural works2,893,850,000285,200,00078,725,000363,925,000⁦13%⁩
Mechanical, electrical & plumbing2,240,400,000139,300,00040,000,000179,300,000⁦8%⁩
Finishes & external works1,400,250,00055,675,00016,375,00072,050,000⁦5%⁩
Testing & commissioning466,750,0008,225,0002,450,00010,675,000⁦2%⁩
Total9,335,000,000836,750,000230,500,0001,067,250,000⁦11%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2024-09-07⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2024-09-09⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2024-09-12⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2024-09-15⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2024-09-18⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-09-07⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2024-09-09⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2024-09-12⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2024-09-15⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-09-18⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2024-10-30⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-07-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

18 September 2024

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2024-09-18 13:00

15 September 2024

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2024-09-15 13:00

12 September 2024

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2024-09-12 13:00

9 September 2024

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2024-09-09 13:00

7 September 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-09-07 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close