Certificate ⁦30⁩ — June 2026

Aleppo 230 kV substations — supply, installation & civil works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
30
Date
⁦2026-07-05⁩
Reference
PAY-2024-003-30

Interim payment certificate no. (⁦30⁩)

For the work of June 2026

Contract number
PSA/2024/003
Tender file no.
2401220043
Contract
Aleppo 230 kV substations — supply, installation & civil works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Aleppo 230 kV Substations Rehabilitation
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
SYP8,800,000,000
Current contract value
SYP9,335,000,000including variations of SYP 535M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date6,390,000,000
2Less: previous certificates(6,304,000,000)
3Value of work in this certificate86,000,000
4Less: retention (⁦10%⁩)(8,600,000)
5Less: advance payment recovery (⁦10%⁩)(8,600,000)
6Less: delay and breach penalties0
7Total deductions(17,200,000)
8Net amount payable to the contractorSYP68,800,000

Amount in words: Sixty-eight million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 639M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation653,450,000647,500,0005,950,000653,450,000⁦100%⁩
Earthworks & foundations1,680,300,0001,663,175,00017,125,0001,680,300,000⁦100%⁩
Concrete & structural works2,893,850,0002,454,025,00033,475,0002,487,500,000⁦86%⁩
Mechanical, electrical & plumbing2,240,400,0001,054,400,00019,125,0001,073,525,000⁦48%⁩
Finishes & external works1,400,250,000422,475,0008,850,000431,325,000⁦31%⁩
Testing & commissioning466,750,00062,425,0001,475,00063,900,000⁦14%⁩
Total9,335,000,0006,304,000,00086,000,0006,390,000,000⁦68%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2026-07-05⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-07-07⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-07-10⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-07-13⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-07-16⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-05⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2026-07-07⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-07-10⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-07-13⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-16⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-02-28⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

16 July 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-07-16 13:00

13 July 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-07-13 13:00

10 July 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-07-10 13:00

7 July 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-07-07 13:00

5 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-05 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close