Certificate ⁦24⁩ — December 2025

Aleppo 230 kV substations — supply, installation & civil works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
24
Date
⁦2026-01-12⁩
Reference
PAY-2024-003-24

Interim payment certificate no. (⁦24⁩)

For the work of December 2025

Contract number
PSA/2024/003
Tender file no.
2401220043
Contract
Aleppo 230 kV substations — supply, installation & civil works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Aleppo 230 kV Substations Rehabilitation
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
SYP8,800,000,000
Current contract value
SYP9,335,000,000including variations of SYP 535M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date5,551,250,000
2Less: previous certificates(5,330,000,000)
3Value of work in this certificate221,250,000
4Less: retention (⁦10%⁩)(22,125,000)
5Less: advance payment recovery (⁦10%⁩)(22,125,000)
6Less: delay and breach penalties0
7Total deductions(44,250,000)
8Net amount payable to the contractorSYP177,000,000

Amount in words: One hundred seventy-seven million Syrian pounds only

Retention held up to this certificate: SYP 555.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation653,450,000633,750,00019,700,000653,450,000⁦100%⁩
Earthworks & foundations1,680,300,0001,588,375,00053,625,0001,642,000,000⁦98%⁩
Concrete & structural works2,893,850,0001,816,775,00076,200,0001,892,975,000⁦65%⁩
Mechanical, electrical & plumbing2,240,400,000885,625,00046,975,000932,600,000⁦42%⁩
Finishes & external works1,400,250,000353,450,00021,250,000374,700,000⁦27%⁩
Testing & commissioning466,750,00052,025,0003,500,00055,525,000⁦12%⁩
Total9,335,000,0005,330,000,000221,250,0005,551,250,000⁦59%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2026-01-12⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-01-14⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-01-17⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-20⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-23⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-12⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2026-01-14⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-01-17⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-01-20⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-23⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-02-28⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

23 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-23 13:00

20 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-20 13:00

17 January 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-01-17 13:00

14 January 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-01-14 13:00

12 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-12 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close