Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 24
- Date
- 2026-01-12
- Reference
- PAY-2024-003-24
Interim payment certificate no. (24)
For the work of December 2025
- Contract number
- PSA/2024/003
- Tender file no.
- 2401220043
- Contract
- Aleppo 230 kV substations — supply, installation & civil works
- Contractor
- Al-Shahbaa Construction & Rehabilitation Co.
- Contractor tax number
- TX-415685
- Project
- Aleppo 230 kV Substations Rehabilitation
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- SYP8,800,000,000
- Current contract value
- SYP9,335,000,000including variations of SYP 535M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 5,551,250,000 |
| 2 | Less: previous certificates | (5,330,000,000) |
| 3 | Value of work in this certificate | 221,250,000 |
| 4 | Less: retention (10%) | (22,125,000) |
| 5 | Less: advance payment recovery (10%) | (22,125,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (44,250,000) |
| 8 | Net amount payable to the contractor | SYP177,000,000 |
Amount in words: One hundred seventy-seven million Syrian pounds only
Retention held up to this certificate: SYP 555.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 653,450,000 | 633,750,000 | 19,700,000 | 653,450,000 | 100% |
| Earthworks & foundations | 1,680,300,000 | 1,588,375,000 | 53,625,000 | 1,642,000,000 | 98% |
| Concrete & structural works | 2,893,850,000 | 1,816,775,000 | 76,200,000 | 1,892,975,000 | 65% |
| Mechanical, electrical & plumbing | 2,240,400,000 | 885,625,000 | 46,975,000 | 932,600,000 | 42% |
| Finishes & external works | 1,400,250,000 | 353,450,000 | 21,250,000 | 374,700,000 | 27% |
| Testing & commissioning | 466,750,000 | 52,025,000 | 3,500,000 | 55,525,000 | 12% |
| Total | 9,335,000,000 | 5,330,000,000 | 221,250,000 | 5,551,250,000 | 59% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Karim Al-Ibrahim
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Maher Al-Hamawi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar