Certificate ⁦26⁩ — February 2026

Aleppo 230 kV substations — supply, installation & civil works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
26
Date
⁦2026-03-11⁩
Reference
PAY-2024-003-26

Interim payment certificate no. (⁦26⁩)

For the work of February 2026

Contract number
PSA/2024/003
Tender file no.
2401220043
Contract
Aleppo 230 kV substations — supply, installation & civil works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Aleppo 230 kV Substations Rehabilitation
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
SYP8,800,000,000
Current contract value
SYP9,335,000,000including variations of SYP 535M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date5,912,500,000
2Less: previous certificates(5,727,000,000)
3Value of work in this certificate185,500,000
4Less: retention (⁦10%⁩)(18,550,000)
5Less: advance payment recovery (⁦10%⁩)(18,550,000)
6Less: delay and breach penalties0
7Total deductions(37,100,000)
8Net amount payable to the contractorSYP148,400,000

Amount in words: One hundred forty-eight million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 591.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation653,450,000638,600,00014,850,000653,450,000⁦100%⁩
Earthworks & foundations1,680,300,0001,638,400,00041,900,0001,680,300,000⁦100%⁩
Concrete & structural works2,893,850,0002,060,050,00067,175,0002,127,225,000⁦74%⁩
Mechanical, electrical & plumbing2,240,400,000953,125,00040,175,000993,300,000⁦44%⁩
Finishes & external works1,400,250,000380,750,00018,350,000399,100,000⁦29%⁩
Testing & commissioning466,750,00056,075,0003,050,00059,125,000⁦13%⁩
Total9,335,000,0005,727,000,000185,500,0005,912,500,000⁦63%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2026-03-11⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-03-13⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-03-16⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-03-19⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-03-22⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-11⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2026-03-13⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-03-16⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-03-19⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-22⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-02-28⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

22 March 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-03-22 13:00

19 March 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-03-19 13:00

16 March 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-03-16 13:00

13 March 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-03-13 13:00

11 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-11 09:00