Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 11
- Date
- 2025-01-01
- Reference
- PAY-2024-003-11
Interim payment certificate no. (11)
For the work of December 2024
- Contract number
- PSA/2024/003
- Tender file no.
- 2401220043
- Contract
- Aleppo 230 kV substations — supply, installation & civil works
- Contractor
- Al-Shahbaa Construction & Rehabilitation Co.
- Contractor tax number
- TX-415685
- Project
- Aleppo 230 kV Substations Rehabilitation
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- SYP8,800,000,000
- Current contract value
- SYP9,335,000,000including variations of SYP 535M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 2,045,000,000 |
| 2 | Less: previous certificates | (1,801,500,000) |
| 3 | Value of work in this certificate | 243,500,000 |
| 4 | Less: retention (10%) | (24,350,000) |
| 5 | Less: advance payment recovery (10%) | (24,350,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (48,700,000) |
| 8 | Net amount payable to the contractor | SYP194,800,000 |
Amount in words: One hundred ninety-four million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 204.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 653,450,000 | 293,350,000 | 36,900,000 | 330,250,000 | 51% |
| Earthworks & foundations | 1,680,300,000 | 456,775,000 | 58,575,000 | 515,350,000 | 31% |
| Concrete & structural works | 2,893,850,000 | 614,050,000 | 83,300,000 | 697,350,000 | 24% |
| Mechanical, electrical & plumbing | 2,240,400,000 | 299,875,000 | 43,675,000 | 343,550,000 | 15% |
| Finishes & external works | 1,400,250,000 | 119,825,000 | 18,225,000 | 138,050,000 | 10% |
| Testing & commissioning | 466,750,000 | 17,625,000 | 2,825,000 | 20,450,000 | 4% |
| Total | 9,335,000,000 | 1,801,500,000 | 243,500,000 | 2,045,000,000 | 22% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Karim Al-Ibrahim
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Maher Al-Hamawi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar