Certificate ⁦17⁩ — June 2025

Aleppo 230 kV substations — supply, installation & civil works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
17
Date
⁦2025-06-23⁩
Reference
PAY-2024-003-17

Interim payment certificate no. (⁦17⁩)

For the work of June 2025

Contract number
PSA/2024/003
Tender file no.
2401220043
Contract
Aleppo 230 kV substations — supply, installation & civil works
Contractor
Al-Shahbaa Construction & Rehabilitation Co.
Contractor tax number
TX-415685
Project
Aleppo 230 kV Substations Rehabilitation
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
SYP8,800,000,000
Current contract value
SYP9,335,000,000including variations of SYP 535M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date3,757,750,000
2Less: previous certificates(3,494,000,000)
3Value of work in this certificate263,750,000
4Less: retention (⁦10%⁩)(26,375,000)
5Less: advance payment recovery (⁦10%⁩)(26,375,000)
6Less: delay and breach penalties0
7Total deductions(52,750,000)
8Net amount payable to the contractorSYP211,000,000

Amount in words: Two hundred eleven million Syrian pounds only

Retention held up to this certificate: SYP 375.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation653,450,000569,950,00036,925,000606,875,000⁦93%⁩
Earthworks & foundations1,680,300,000887,000,00059,950,000946,950,000⁦56%⁩
Concrete & structural works2,893,850,0001,190,825,00090,575,0001,281,400,000⁦44%⁩
Mechanical, electrical & plumbing2,240,400,000580,475,00050,825,000631,300,000⁦28%⁩
Finishes & external works1,400,250,000231,675,00021,975,000253,650,000⁦18%⁩
Testing & commissioning466,750,00034,075,0003,500,00037,575,000⁦8%⁩
Total9,335,000,0003,494,000,000263,750,0003,757,750,000⁦40%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Karim Al-Ibrahim

Al-Ibrahim⁦2025-06-23⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-06-25⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2025-06-28⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-07-01⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-07-04⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-06-23⁩

    Eng. Karim Al-Ibrahim

  2. Engineer verifies quantities⁦2025-06-25⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-06-28⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2025-07-01⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-04⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2025-07-20⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-07-01⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

4 July 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-07-04 13:00

1 July 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-07-01 13:00

28 June 2025

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2025-06-28 13:00

25 June 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-06-25 13:00

23 June 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-06-23 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close