SO-1.1 · Stimulate growth, restore production and attract investment

Integrated government financial systems

Off trackDelivered wholly through projectsEconomic Recovery & Monetary Stability

The integrated public financial management system for budget, procurement and payroll across the ministries, Ministry of Finance e-archiving, and government HR self-service.

⁦75%⁩

Initiative weighted progress

⁦75.4%⁩

Σ each project’s contribution × its actual progress, over the shares that count

Linked projects’ progress

⁦75.4%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

SYP2.3B

3 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
Integrated Public Financial Management System — Phase 1

PRJ-2026-001

Primary⁦60%⁩⁦61%⁩⁦36.6%⁩
Ministry of Finance e-Archiving

PRJ-2026-017

Primary⁦25%⁩⁦95%⁩⁦23.8%⁩
Government HR System — Employee Self-Service

PRJ-2026-032

Primary⁦15%⁩⁦100%⁩⁦15.0%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦75.4%⁩ points ÷ shares counted ⁦100%⁩ = ⁦75.4%⁩

Initiative progress

The initiative runs wholly through its projects, so its progress is theirs: ⁦75.4%⁩

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

Budget, procurement and payroll across the ministries on the integrated public financial management system, Ministry of Finance e-archiving, and self-service for public employees.

Outputs

  • The integrated public financial management system
  • The Ministry of Finance e-archive
  • Government HR self-service

Delivery phases

  • HR self-service

    2024-05-05 — 2025-09-21

  • e-Archiving

    2025-01-19 — 2026-11-15

  • The financial management system

    2025-01-12 — 2027-02-27

Today · 2026-10-28

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: Integrated Public Financial Management System — Phase 1

1Deliverable weight in the project

⁦40.0%⁩

Weight of «Build» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦16.4%⁩

Its relative weight in Government Digital Infrastructure & Systems Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦60%⁩

Its contribution to «Integrated government financial systems»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Obstacle in the wayHighOpen

    Legacy procurement data from the ministries migrating slower than planned

    Response: Cleanse before migrating and defer the pre-2022 archive

    Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy

Deviation

Budget: projects total SYP 2.3B against the estimate SYP 2.2B

Schedule: last project ends ⁦2027-02-27⁩ against the initiative end ⁦2027-02-28⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Higher Council resolution HCED-2026-032026-03-25

No change requests on this item since the plan was approved.