SO-5.1 · Integrated digital government services for citizens

Digital justice

On trackIncludes non-project workGovernance & Digital Transformation

Electronic filing and judicial notification in the courts, managed sessions and records, and case status without a visit.

⁦85%⁩

Initiative weighted progress

⁦84.7%⁩

Projects’ contribution × progress, plus the other work’s share × its progress

Linked projects’ progress

⁦91.0%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

SYP460M

1 primary project

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
e-Litigation & Judicial Notification Platform — Release 2

PRJ-2026-008

Primary⁦70%⁩⁦91%⁩⁦63.7%⁩

Non-project work

Training judges and court clerks and updating the notification procedures and templates

Other work⁦30%⁩⁦70%⁩⁦21.0%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦63.7%⁩ points ÷ shares counted ⁦70%⁩ = ⁦91.0%⁩

Initiative progress

(⁦63.7%⁩ points from projects + ⁦21.0%⁩ from other work) ÷ ⁦100%⁩ = ⁦84.7%⁩

Scope, outputs & phases

As approved with the initiative: what is in scope, what it delivers, and its delivery phases on the timeline.

Scope

Electronic filing, judicial notification and session management in the governorate courts, and updated notification procedures and templates with the Ministry of Justice.

Outputs

  • e-Litigation & judicial notification platform — Release 2
  • An e-notification procedure manual
  • Court staff trained in the governorates

Delivery phases

  • Update the procedures and templates

    2025-05-04 — 2025-12-31

  • Build Release 2

    2025-08-01 — 2026-11-30

  • Training and launch

    2026-11-01 — 2026-12-31

Today · 2026-10-28

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: e-Litigation & Judicial Notification Platform — Release 2

1Deliverable weight in the project

⁦40.0%⁩

Weight of «Build» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦15.6%⁩

Its relative weight in Digital Government Services & Data Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦70%⁩

Its contribution to «Digital justice»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.

Risks, obstacles & deviations

The initiative’s own risks and obstacles, the highest open risks of its projects, and the budget and schedule deviation.

  • Possible riskLowOpen

    Weak network connections at some remote courts

    Response: Connect them to the government backbone, starting with the Damascus–Homs segment

    Dr. Nisreen Al-ShoufiDr. Nisreen Al-ShoufiDirector, Legal Affairs & Secretary of the National Steering CommitteeP-052nisreen.alshoufi@psa.gov.sy

Highest risks of the linked projectsRisk register

No high open risks on its projects.

Deviation

Budget: projects total SYP 460M against the estimate SYP 600M

Schedule: last project ends ⁦2026-11-26⁩ against the initiative end ⁦2026-12-31⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Higher Council resolution HCED-2026-032026-03-25

No change requests on this item since the plan was approved.